Jump to content
 







Main menu
   


Navigation  



Main page
Contents
Current events
Random article
About Wikipedia
Contact us
Donate
 




Contribute  



Help
Learn to edit
Community portal
Recent changes
Upload file
 








Search  

































Create account

Log in
 









Create account
 Log in
 




Pages for logged out editors learn more  



Contributions
Talk
 



















Contents

   



(Top)
 


1 Route  





2 History  





3 Future planning  



3.1  Lena crossing  





3.2  Eastwards  







4 References  














AmurYakutsk Mainline






Беларуская
Беларуская (тарашкевіца)
Български
Català
Čeština
Deutsch
Français
Latviešu
Lietuvių
Magyar
Nederlands

Polski
Русский
Svenska
Українська

 

Edit links
 









Article
Talk
 

















Read
Edit
View history
 








Tools
   


Actions  



Read
Edit
View history
 




General  



What links here
Related changes
Upload file
Special pages
Permanent link
Page information
Cite this page
Get shortened URL
Download QR code
Wikidata item
 




Print/export  



Download as PDF
Printable version
 




In other projects  



Wikimedia Commons
 
















Appearance
   

 





Coordinates: 62°0242N 129°4348E / 62.045°N 129.730°E / 62.045; 129.730
 

From Wikipedia, the free encyclopedia
 

(Redirected from Amur Yakutsk Mainline)

Amur–Yakutsk Mainline
Overview
Other name(s)Yakutian Railway
Native nameАмуро-Якутская магистраль
StatusOperational
LocaleRussian Far East
Termini
  • Nizhny Bestyakh
  • Continues fromTrans–Siberian Railway
    Stations50
    Service
    Type
  • Freight rail
  • System
  • Yakutian Railway (Neryungri–Nizhny Bestyakh)
  • Operator(s)
  • Yakutian Railway
  • History
    Commenced5 April 1972 (1972-04-05)
    Opened2 November 1976 (1976-11-02)
    Completed15 November 2011 (2011-11-15)
    Technical
    Line length767 km (477 mi)
    Number of tracks1
    Track gauge1,520 mm (4 ft 11+2732 in) Russian gauge

    Route map

    km
    Trans-Siberian Railway
    Bamovskaya (km 7,273)

    0

    0,000

    0,019
    Shturm

    Maly Oldoy

    49
    Murtygit

    66
    Purikan

    82
    Anosovskaya
    (Anosovsky)

    Maly Oldoy

    94
    Silip

    Ushumun

    112
    Zabolotny

    Tynda

    133
    Belenkaya

    Tynda

    160
    Seti

    179
    Tynda

    0,000

    0,000
    Tynda

    190
    Shakhtaum
    (Vostochny)

    205
    Bestuzhevo

    0,000

    0,000

    225
    Gilyuy

    250
    Mogot

    Mogot

    269
    Rikhard Zorgye

    285
    border

    0,000

    0,285
    Yakutsky

    298
    Nagornaya-Yakutskaya

    Timpton

    319
    Ayam

    319
    Nagorny-Tunnel (
    1300 m
    1422 yd
    )

    340
    Zolotinka

    Iengra

    357
    Okurdan

    Gorbyllakh

    382
    Oborcho

    399
    Berkakit

    408
    Neryungri-Passazhirskaya

    0,000

    0,416
    Neryungri-Grusovaya

    Chulman

    Chulman

    419
    Denisovsky

    Chulman

    Chulman

    430
    Chulman

    Chulman

    444
    Chulbas

    455
    Tenisty

    485
    Khatymi
    (Bolshoy Khatymi)

    Khatyma

    504
    Ogonyer

    548
    Tayozhny

    Bolshoy Nimnyr River

    608
    Bolshoy Nimnyr

    653
    Seligdar

    669
    Kosarevsky

    686
    Aldan

    0,000

    0,716
    Kuranakh

    Yakokit

    767
    Tommot

    0,000

    0,000

    Bolotny

    869
    Amga

    Kyrbykan

    932
    Karbykan

    Ulu

    962
    Ulu, Russia

    982
    Kyurgelyakh

    1,061
    Khaniyerdakh

    Munduruchchu

    1,085
    Olen
    (Sakha)

    Lyutenge

    Lyutenka

    1,136
    Kyordyom

    Lyutenge

    Menda

    1,153
    Menda

    1,176
    Rassoloda

    Tamma

    1,136
    Pravaya Lena

    0,000

    0,000
     

    1,209
    Tabaga

    1,228
    Kyurdyugelakh

    1,249
    Chabyda

    1,275
    Yakutsk-Grusovaya
    (freight)

    1,284
    Yakutsk-Passazhirskaya
    (passenger)

    1,288
    Port Rechnoy

    0,000

    0,000
    Tamma

    1,195
    Khaptagay

    1,213
    Nizhny Bestyakh

    0,000

    0,000
    Churapcha

    Megino-Aldan

    Kyubyume

    border

    Susuman

    Orotukan

    Atka

    Palatka

    Sokol

    Magadan

    km

    The Amur–Yakutsk Mainline (Russian: Амуро-Якутская магистраль, Amuro-Yakutskaya Magistral), abbreviated to AYaM (Russian АЯM), is a partially complete railway in eastern Russia, linking the Trans–Siberian Railway and Baikal–Amur Mainline with the Sakha Republic.

    Passenger services on the line go from Tynda to the town of Nizhny Bestyakh, opposite the river from Yakutsk. In November 2011, construction of the railway reached Nizhny Bestyakh.[1] The final step required to bring the railway into the city itself is a combined road and rail bridge, to be constructed upstream of Yakutsk where the river is narrower.

    The railway via Nizhny Bestyakh is planned in the long term to form the start of a railway towards Magadan and possibly even across the Bering Strait.[2]

    Route[edit]

    Map of major railways in Russia, with Trans–Siberian Railway shown in red, BAM in green and Amur Yakutsk Mainline (including "Little BAM") shown in orange

    The line is single-track, excepting the double-track section from Tynda to Bestuzhevo, which is shared with the Baikal–Amur Mainline (BAM). The full length of the line is not electrified.

    As in most of Siberia, the construction and operation of the railway are complicated by the large temperature variations, ranging from under −50 °C (−58 °F) in winter to over 30 °C (86 °F) in summer, as well as the challenges of building on permafrost in difficult terrain.

    The line currently has an official length of 1,213 kilometres (754 miles), branching from the Trans–Siberian railway at Bamovskaya station, near SkovorodinoinAmur Oblast. The line continues north, joining the Baikal–Amur Mainline near Tynda and continuing along the BAM for 27 kilometres (17 miles) before branching northwards at Bestuzhevo. The line in this section crosses the Gilyuy River twice. Shortly after entering the Sakha Republic, the line passes through the 1,300-metre-long (4,300-foot) Nagorny tunnel under the Stanovoy Range.

    In the highlands of southern Sakha Republic, the line crosses numerous further rivers, including the Iyengra and Chulman, before reaching the coal-mining area around Neryungri at around 400 kilometres (250 miles). The settlement of Berkakit, situated 9 kilometres (5.6 miles) south of Neryungri, was founded in 1977 as the base for the railway's operations in the south of the Sakha Republic. Berkakit is the official starting point for the current project to construct the railway to Yakutsk (officially referred to as the Berkakit–Tommot–Yakutsk Line), and the majority of the town's workforce is employed either in management or maintenance of the railway.

    To the north of Neryungri, the railway crosses the Aldan Highlands, before reaching Aldan at kilometre 686, where the main offices of the Yakutia Railways are located. The current terminus of the operating section of the line is Tommot, on the right bank of the Aldan River at kilometer 767.

    Bridge over the Aldan River at Tommot

    Beyond Tommot station, the railway crosses the Aldan on a 350-metre-long (1,150-foot) bridge, the longest on the line (except for the planned bridge over the Lena). From here, the line continues to the settlement of Verkhnyaya Amga (station simply named Amga), where it crosses the Amga River. Provisional goods services began to Amga in 2006, with construction trains travelling as far as Kharbykan.

    Construction reached the settlement of Kerdyom, by the mouth of the Lyutenge on the Lena River, opposite the town of Pokrovsk, by 2008. From here, it was planned to start construction of a 3-kilometre-long (1.9-mile) combined road and rail bridge across the Lena in 2009, in the area of the settlement Tabaga. The line was to continue to the city of Yakutsk, with a passenger terminal to be built, and an extension to the river port.[3]

    With the expected difficulties in building a bridge across the more than 2 km-wide Lena, prone to massive flooding in spring and with moving ice during autumn, there has been much discussion of the rail head remaining on the east bank of the river, terminating in Nizhny Bestyakh, across the river from Yakutsk. This section has been built,[4] the connection over the river to Yakutsk city being postponed. The route via Nizhny Bestyakh will now form the beginning of any further extensions towards Magadan.[5]

    As of early 2014, there were twice weekly trains from Moscow and from Khabarovsk, ending at Neryungri. The travel time from Shturm (1st station of AYaM) to Neryungri (390 km) was 11 hours.[6]

    From 2019, there are passenger trains to Nizhny Bestyakh.[7]

    History[edit]

    Ceremony at Neryungri in 1985, marking the beginning of construction towards Yakutsk

    Construction of the AYaM began in the 1930s, with the construction of the spur line from Bamovskaya to Tynda (then known as Tyndinsky) as part of the planned construction of the Baikal–Amur Mainline. This section began operation in 1935, but was then dismantled in 1940-41 as the Second World War saw the BAM project cancelled and the rails were reused for other projects closer to the front.

    Reconstruction of the Bamovskaya-Tynda section (known as the "Little BAM") began on 5 April 1972, almost two years before the government of the Soviet Union announced the revival of the BAM project in 1974. The start of provisional services on the Little BAM began in November 1976, with full services in October 1977. At the same time, the line was extended northwards, the section Tynda–Berkakit opened in October 1979, extending as far as Neryungri.

    From 1989, construction recommenced from Neryungri towards Chulman. This extension branches a few kilometers before the previous terminus of Neryungri-Gruzovaya (cargo terminal). Traffic was gradually extended to Chulman, Aldan and finally to Tommot, firstly construction and cargo traffic, followed by passenger services. The complete section to Tommot was declared open on 24 August 2004. Since this date a daily passenger service has run between Neryungri and Tommot, covering the 368 Kilometer section in around 8 hours.

    The bridge crossing the Aldan RiverinTommot, at 400 metres (1,300 ft) wide at this point the largest river on the planned route besides the Lena, was completed in the 1990s, although not initially used. A further section of around 60 km was under construction when financial problems halted the project.

    Construction resumed in 2005, with construction traffic able to operate through to Kharbykan by the start of 2007. Cargo traffic currently operates as far as Amga. In early 2009 the construction reached the dual settlements of Pokrovsk/Kyordyom, on the left and right banks of Lena respectively, some 78 km south of Yakutsk.[8]

    The first train was welcomed into Kyordyom on September 25, 2010.[9] The line to Nizhny Bestyakh was officially completed on November 15, 2011, with officials stating that a bridge across the river to Yakutsk would be constructed in the near future.[1][10]

    On July 27, 2019, passenger trains started to go to Nizhny Bestyakh.[7]

    Future planning[edit]

    Lena crossing[edit]

    Planning for the line almost as far as Yakutsk is complete, although there has been debate as to whether the line should end at the settlement of Nizhny Bestyakh, on the opposite bank of the Lena River from Yakutsk, or whether a bridge (or possibly tunnel) should be built. The decision for or against a river crossing depends on a number of questions regarding both costs and engineering challenges. The Lena is at this point more than 2 km wide, has a number of side streams, and can flood the valley to a width of up to 10 km during the snowmelt in spring.

    There is currently no bridge of any kind across the Lena in the Sakha Republic. Air travel is currently the only mode of transport to Yakutsk available year-round; land transport to the outside world is possible via ferry in summer, or by driving across the frozen river in winter. During spring and autumn, the moving ice on the river makes crossings impossible. The dual road-rail bridge would allow year-round land access to the city for the first time.

    The site being considered is across a narrow section of the river near Tabaga, 40 km upstream from Yakutsk.[11]

    On July 14, 2010, in Moscow, a meeting was held to discuss the construction of a tunnel under the Lena river, instead of a bridge. Construction of a tunnel would be quicker and cost less than that of a bridge, as it would not be dependent on seasonal construction hampered by the river freezing over in autumn and breaking up in spring. The flooding situation of the river also makes the tunnel more attractive. However, the annual maintenance costs for a tunnel were estimated to be more than twice that of a bridge. Construction of a tunnel in permafrost also posed engineering challenges.[12][13]

    In July 2013, the federal road agency, Rosavtodor requested a tender to build a three-kilometer road-only bridge over the river connecting Yakutsk to the A360 Lena highway, expecting a cost of $1.7 bn/56 bn RUB, and a 6-year construction period.[14] This was cancelled due to funding being transferred to the new Crimean Bridge.

    In 2015, it was reported that Chinese interests, including the China Railway Construction Corporation, China Development Bank and four other Chinese construction companies, had expressed interest in financing the construction of the bridge.[15] The head of Yakutia said in 2018 that construction could begin in 2020.[16]

    Eastwards[edit]

    Future plans have been proposed for the extension of the railway line further to the east, towards the Kolyma region, Magadan and even Chukotka and a Bering Strait crossing which would link Russia with the United States. The Russian government in 2011 approved the construction of a US$65 billion Siberia-Alaska rail link and a tunnel across the Bering Strait.[2] There are dreams among railroad enthusiasts about high-speed trains between Europe and the United States through Russia, but the Amur–Yakutsk Mainline is mostly too curvy to allow any high speed.

    Plans were announced in May 2012 by the governor of Magadan Oblast to extend the railway 1800 km eastwards of Yakutsk to Moma and onwards to Magadan[17] with construction scheduled to begin in 2016, according to the President of Yakutia.[18] In 2016 the railway project was included in the Federal railway development strategy plan until 2030.[19]

    References[edit]

    1. ^ a b "RUSSIAN BERKAKIT-TOMMOT-NIZHNY BESTYAKH LINE COMPLETED". Archived from the original on 16 April 2014. Retrieved 5 December 2011.
  • ^ a b "Russia Green Lights $65 Billion Siberia-Alaska Rail and Tunnel to Bridge the Bering Strait!". 23 August 2011. Retrieved 23 August 2011.
  • ^ "Sakha Information Server". www.sakha-info.ru. Archived from the original on 6 October 2011. Retrieved 13 January 2022.
  • ^ "Russian Berkakit-Tommot-Nizhny Bestyakh Line Completed". Archived from the original on 16 April 2014. Retrieved 5 December 2011.
  • ^ "After Yakutsk the Railway will go to Magadan". Archived from the original on 1 July 2011. Retrieved 24 November 2010.
  • ^ http://rzd.ru
  • ^ a b Росжелдор издал приказ об открытии для постоянной эксплуатации участка Томмот – Нижний Бестях –Roszheldor issued an order to open for permanent operation of the Tommot - Nizhny Bestyakh section (1 July 2019)
  • ^ "В 2009 году в Амуро-Якутскую магистраль вложат 8,9 млрд рублей". Новости России, СНГ и мира - ИА REGNUM. Retrieved 29 June 2023.
  • ^ "Задачи по строительству железной дороги будут выполнены — ЯСИА (Russian)" (in Russian). Archived from the original on 9 October 2011.
  • ^ "News | Russian Railways". Archived from the original on 25 December 2011. Retrieved 22 December 2011.
  • ^ "The bridge across the Lena River near Yakutsk City, Yakutia - Transmost". www.transmost.ru. Retrieved 29 June 2023.
  • ^ "Yakutian-Sakha Informational Agency". Archived from the original on 9 March 2012. Retrieved 18 July 2010.
  • ^ http://egorborisov.ru/content/view/731/18/[permanent dead link] in Russian [dead link]
  • ^ Lena River Bridge to Provide Hope and Fruit
  • ^ "Could Chinese money finally bridge the Lena River and usher economic upsurge?". siberiantimes.com. Retrieved 29 June 2023.
  • ^ "Мост через реку Лену в Якутии начнут возводить в 2020 году" [The bridge across the Lena River in Yakutia will begin to be built in 2020] (in Russian). 25 December 2018.
  • ^ International2012-05-19T04:00:00+01:00, Railway Gazette. "News in Brief - May 2012". Railway Gazette International. Retrieved 29 June 2023.{{cite web}}: CS1 maint: numeric names: authors list (link)
  • ^ "Строительство железной дороги Якутск – Мома – Магадан начнется в 2016 году - MagadanMedia". magadanmedia.ru. Retrieved 29 June 2023.
  • ^ "Строительство железной дороги из Магадана в Якутск обсудят с замминистра транспорта РФ" [Construction of a railway from Magadan to Yakutsk will be discussed with the Deputy Minister of Transport of the Russian Federation] (in Russian). 11 August 2016. Retrieved 8 August 2019.
  • 62°02′42N 129°43′48E / 62.045°N 129.730°E / 62.045; 129.730


    Retrieved from "https://en.wikipedia.org/w/index.php?title=Amur–Yakutsk_Mainline&oldid=1185014999"

    Categories: 
    Railway lines in Russia
    Rail transport in the Soviet Union
    Rail transport in Siberia
    Rail transport in the Sakha Republic
    Hidden categories: 
    CS1 Russian-language sources (ru)
    All articles with dead external links
    Articles with dead external links from October 2016
    Articles with permanently dead external links
    Articles with dead external links from July 2022
    CS1 maint: numeric names: authors list
    Pages using gadget WikiMiniAtlas
    Articles with short description
    Short description is different from Wikidata
    Use dmy dates from September 2022
    Articles containing Russian-language text
    Articles with Structurae structure identifiers
    Coordinates on Wikidata
     



    This page was last edited on 14 November 2023, at 01:02 (UTC).

    Text is available under the Creative Commons Attribution-ShareAlike License 4.0; additional terms may apply. By using this site, you agree to the Terms of Use and Privacy Policy. Wikipedia® is a registered trademark of the Wikimedia Foundation, Inc., a non-profit organization.



    Privacy policy

    About Wikipedia

    Disclaimers

    Contact Wikipedia

    Code of Conduct

    Developers

    Statistics

    Cookie statement

    Mobile view



    Wikimedia Foundation
    Powered by MediaWiki