1 Background  





2 Configurations  



2.1  Three rails  





2.2  Four rails  





2.3  Triple gauge  





2.4  More than three gauges  







3 Alternatives  





4 Dual-gauge railways by nation  





5 See also  





6 Notes  



6.1  Notes to gallery photos  







7 References  





8 Further reading  





9 External links  














Dual gauge







Dansk
Deutsch
Español
Français

Latviešu
Nederlands

Norsk bokmål
Norsk nynorsk
Polski
Português
Русский
Svenska

Türkçe
Українська

 

Edit links
 









Article
Talk
 

















Read
Edit
View history
 








Tools
   


Actions  



Read
Edit
View history
 




General  



What links here
Related changes
Upload file
Special pages
Permanent link
Page information
Cite this page
Get shortened URL
Download QR code
Wikidata item
 




Print/export  



Download as PDF
Printable version
 




In other projects  



Wikimedia Commons
 
















Appearance
   

 






From Wikipedia, the free encyclopedia
 

(Redirected from Mixed gauge)

In railway engineering, "gauge" is the transverse distance between the inner surfaces of the heads of two rails, which for the vast majority of railway lines is the number of rails in place. However, it is sometimes necessary for track to carry railway vehicles with wheels matched to two different gauges. Such track is described as dual gauge – achieved either by addition of a third rail, if it will fit, or by two additional rails. Dual-gauge tracks are more expensive to configure with signals and sidings, and to maintain, than two separate single-gauge tracks. It is therefore usual to build dual-gauge or other multi-gauge tracks only when necessitated by lack of space or when tracks of two different gauges meet in marshalling yards or passenger stations. Dual-gauge tracks are by far the most common configuration, but triple-gauge tracks have been built in some situations.

Background[edit]

The rail gauge is the most fundamental specification of a railway. Rail tracks and wheelsets are built within engineering tolerances that allow optimum lateral movement of the wheelsets between the rails. Pairs of rails that become too wide or narrow in gauge will cause derailments, especially if in excess of normal gauge-widening on curves.[1][note 1]

Given the requirement for gauge to be within very tight limits, when the designed distance between the pair of wheels on a wheelset differs even slightly from that of others on a railway, track must be built to two specific gauges. That is achieved in a variety of ways: most commonly by adding a third rail, more rarely by adding another pair of rails; and rarer still, when three gauges are present, by four rails.

Configurations[edit]

Baseplate on dual-gauge track showing the minimum practicable gap between the bases of two rails – about 40 mm (11/2 in) – which determines the minimum difference in gauges possible in a three-rail configuration
Interactive 3D view

An interactive 3D view of dual-gauge track components is
here

Dual-gauge track can consist of three rails, sharing one "common" rail; or four rails, with the rails of the narrower gauge lying between those of the broader gauge. In the three-rail configuration, wear and tear of the common rail is greater than with the two other outer rails. In dual gauge lines, turnouts (railroad switches) are more complex than in single-gauge track, and trains must be safely signalled on both of the gauges. Track circuits and mechanical interlocking must also operate on both gauges.[4]

Multi-gauge track is very often associated with a break-of-gauge station, where rail vehicles or vehicle contents are transferred from one gauge to another. A break of gauge causes delay and increases congestion, especially on single-track lines. Essentially, two trains are required to do what a single train would normally accomplish. When traffic passes mainly in one direction, full wagons taken to the border have to be returned as empties, and a train of empty wagons has to be brought to the break of gauge from the other side to fetch the cargo. Congestion is also caused by unloading and reloading.[5][6]: 74–75  The problem is worsened when there is a disparity between the capacity of locomotives and vehicles on the two gauges: typically, one broad-gauge trainload needs three narrow-gauge trains to carry.[7]

Three rails[edit]

Configuration of dual-gauge (1600 mm and 1435 mm) track.

Constructing dual-gauge track with three rails is possible when the two adjacent rails can be separated at the base by at least the space required by rail fastening hardware such as spikes and or rail clips – typically 40 millimetres (1.6 inches). If the two gauges are closer than that, four rails must be used. Depending on the rail fasteners used and the weight of rails (heavy rails are bigger), the practicable difference between the two gauges is in the range 145 millimetres (5.7 inches) to 200 millimetres (7.9 inches).[8]

Gallery: Dual gauge (3 rails)


1600 / 1000 mm
(5 ft 3 / 3 ft 33/8 in)
[a]
1600 / 1435 mm
(5 ft 3 / 4 ft 81/2 in).
[b]


1435 / 891 mm
(4 ft 81/2 / 2 ft 113/32 in)
[c]
1435 / 1000 mm
(4 ft 81/2 / 3 ft 33/8 in)
[d]

1435 / 1067 mm
(4 ft 81/2 / 3 ft 6 in)
[e]

Four rails[edit]

Four-rail arrangement of standard and metre gauge on the Chemin de Fer de la Baie de Somme. A 435 mm difference in gauge can also be accommodated in a three-rail configuration.

In some places, the dimensions of two gauges needing to be collocated are too close to allow a three-rail configuration – for example:

In such cases, four rails are needed to provide the dual gauge.

Four rails might also be installed because of other engineering or operational factors, even though three rails would suffice: an example is on the Chemin de Fer de la Baie de Somme (Somme Bay railway), which combines standard and metre gauge – 435 millimetres (17.1 inches) different, well within the parameters for three rails.

Four rails are necessary where the centre-line of rail vehicles on both tracks must be closely aligned with the centre-line of the track in tunnels or other constricted locations. Such configurations, when they revert back to standard parallel lines as soon as room is available, are termed "gauntlet track" (US: "gantlet track").[9][1]

Four rails must be placed identically on either side of the central axis of dual-gauge turntables (and six rails on triple-gauge turntables) so that they match the configuration of the fixed rails leading to and from the turntable, regardless of the direction in which the turntable is facing.

Gallery: Dual gauge (4 rails)


1435 / 1000 mm
(4 ft 81/2 / 3 ft 338 in).
In the foreground, the narrow gauge diverges via a fixed-rail configuration. [f]
1520 / 1435 mm
(4 ft 1127/32 / 4 ft 81/2 in).
The gauges of this track are as follows (numbering the rails from left to right). 1520 mm gauge: rails 1 and 3; 1435 mm gauge: rails 2 and 4. [g]

1524 / 1435 mm
(5 ft 0 / 4 ft 81/2 in).
A line comprising European standard gauge and "Russian" gauge, a legacy of the former satellite states of the Soviet Union. The 89 mm difference between the two gauges is too small to allow a three-rail configuration. [h]

Triple gauge[edit]

Cross-section of triple-gauge track at Gladstone and Peterborough, South Australia, before gauge standardisation. The three gauges require the respective gaps between the outer and inner rails to be different, unlike four-rail dual gauge.

In rare situations, three different gauges may converge on to a rail yard and triple-gauge track is needed to meet the operational needs of the break-of-gauge station – most commonly where there is insufficient space to do otherwise. Construction and operation of triple-gauge track and its signalling, however, involves immense cost and disruption, and is undertaken when no other alternative is available.[10]

Gallery: Triple gauge (4 rails)


1600 / 1435 / 1067 mm
(5 ft 3 / 4 ft 81/2 / 3 ft 6 in).
Turnout, 4-rail triple-gauge both ways, from the points end. [i]
1600 / 1435 / 1067 mm
(5 ft 3 / 4 ft 81/2 / 3 ft 6 in).
Turnout, 4-rail triple-gauge both ways, from the crossing end. [j]


1600 / 1435 / 1067 mm
(5 ft 3 / 4 ft 81/2 / 3 ft 6 in). Three-rail dual-gauge track is joined by four-rail triple-gauge. [k]
1600 / 1435 / 1067mm
(5 ft 3 / 4 ft 81/2 in / 3 ft 6 in).
Standard-gauge car on 4-rail triple-gauge track. Narrow gauge track is two central rails; broad gauge is far left rail and second from right. [l]


1600 / 1435 / 1067 mm
(5 ft 3 / 4 ft 81/2 / 3 ft 6 in).
A six-rail triple-gauge turntable. It must always present the same positioning of rails at both ends, so all four rails must be symmetrical to the central axis. This is made possible only by reducing the profile of the middle rail on either side. [m]
1600 / 1435 / 1067 mm
(5 ft 3 / 4 ft 81/2 / 3 ft 6 in).
When the Sydney–Perth rail corridor was converted to standard gauge in the late 1960s, dual-gauge track in the Gladstone yard had to be replaced by all-new triple-gauge track. The result was an inordinately complex marshalling yard. [n]

The following table shows localities where triple gauge has been necessary.

Occurrences of triple gauge
Place Narrowest
gauge
Middle
gauge
Broadest
gauge
Notes
Volos, Greece 600 mm (1 ft 11+58 in) 1000 mm (3 ft 3+38 in) 1435 mm (4 ft 8+12 in) 600 mm (1 ft 11+58 in) gauge closed in the 1970s, 1000 mm (3 ft 3+38 in) gauge closed in 1998
Jenbach, Austria 760 mm (2 ft 5+1516 in) Still in use[when?]
Montreux, Switzerland 800 mm (2 ft 7+12 in)
Capolago, Switzerland Metre gauge line closed in 1950
Växjö, Sweden 891 mm (2 ft 11+332 in) 1067 mm (3 ft 6 in) Until 1974 or later[11]
Vynohradiv, Ukraine 750 mm (2 ft 5+12 in) 1435 mm (4 ft 8+12 in) 1520 mm (4 ft 11+2732 in) Standard and broad gauge track is track plait[ambiguous] between Halmeu, Romania and Čierna nad Tisou, Slovakia, near Ukraine. The narrow-gauge track belongs to Borzhava narrow-gauge railway.[ambiguous] All still in use.[when?]
Latour-de-Carol, France 1000 mm (3 ft 3+38 in) 1668 mm (5 ft 5+2132 in) Still in use[when?]
Hendaye, France
Gladstone, South Australia[note 2] 1067 mm (3 ft 6 in) 1600 mm (5 ft 3 in) 1968–1983
(Some has been reconstructed at the National Railway Museum, Port Adelaide.)[14]
Peterborough, South Australia 1968–1983. (Some has been preserved at the Steamtown Heritage Rail Centre in Peterborough.)[15]
Toronto, Canada 1676 mm (5 ft 6 in) Reported as impending in 1872.[16] Subsequently convertedto1435 mm (4 ft 8+12 in) gauge.
Gallery: Multi-gauge devices


1600 / 1067 mm
(5 ft 3 / 3 ft 6 in).
A dual-gauge centraliser that directs narrow-gauge livestock cars to the centre of the broad gauge so that they can be shunted without snagging the platforms. [o]
1600 / 1435 mm
(5 ft 3 / 4 ft 81/2 in).
A simple dual-gauge common-rail change-over device. It directs standard-gauge rolling stock from the common rail in the left foreground to the right-hand rail in readiness for the turnout in the distance. [p]


1600 / 1435 / 1067 mm
(5 ft 3 / 4 ft 81/2 / 3 ft 6 in).
Triple-gauge common-rail change-over device: from one common rail (right foreground) to narrow gauge in the middle (in the distance). [q]
1600 / 1435 / 1067 mm
(5 ft 3 / 4 ft 81/2 / 3 ft 6 in).
A four-rail triple-gauge track that joins a three-rail dual-gauge track. The change-over device in the foreground directs standard-gauge rolling stock into a four-rail configuration. [r]

More than three gauges[edit]

The Gorton Foundry of Beyer, Peacock & Company was typical of locomotive and rolling stock manufacturers that exported to many countries. This track of four gauges traversed two turntables, requiring the rails to be centralised.

Three gauges are the maximum found on operating railway lines and in railway yards, but some rolling stock manufacturers collocate more than three lines in their works, depending on the particular gauges of their customers.

Alternatives[edit]

Rollbocks compared to transporter wagons
Standardised containers have revolutionised rail, road and sea freight transport. Although mechanisation has sped up handling, moving containers from one train to another because of different rail gauges is costly and inefficient.

Transfer of freight and passengers between different gauges does not necessarily involve dual-gauge track: there may simply be two tracks that approach either side of a platform without overlapping. In Australia, 13 break-of-gauge stations existed by 1945 as a result of longstanding interstate rivalries: three different gauges had persisted since the 1850s and the five mainland state capitals were not linked by standard gauge until 1995.[17] Huge costs and long delays were imposed by trans-shipment of freight at break-of-gauge stations, whether manually, by gantry crane or by wheelset or bogie exchange.[6]: 67  During World War II, breaks of gauge in Australia added immense difficulty to the war effort by needing extra locomotives and rolling stock, and more than 1600 service personnel and a large pool of civilians, at transfer points for an annual average transfer of about 1.8 million tonnes of freight.[18]

To cost and inefficiency was added, in the case of passengers, considerable inconvenience. In 1896, at Albury station on the Sydney–Melbourne railway, famed American writer Samuel Clemens (Mark Twain) had to change trains in the middle of a "biting-cold" night in 1896 and there formed his pungent view of "the paralysis of intellect that gave that idea birth".[19]

In some locations, an alternative to building long lengths of dual-gauge track has been to change the wheels on rolling stock, either by dropping and changing wheelsets from four-wheeled vehicles or exchanging bogies (US: trucks) under eight-wheeled vehicles. With this arrangement, a short length of dual-gauge track is only needed within the facility. A benefit is that the contents of fully loaded cars are not disturbed. The scheme was first adopted on the French–Spanish border and in Poland. It introduces delay into transit times compared with dual-gauge operation, but is much quicker than trans-shipping: when introduced in 1962 in Melbourne, Australia, on the route between Sydney and Adelaide, the freight handling time per train dropped from five days to less than two. The process involved disconnecting the brake rigging and bogie centre pins have to be disconnected before the vehicle is lifted and new bogies are wheeled underneath.[20][note 3]

In Europe, a similar principle embodies low-profile, small-wheeled transporter wagons, which carry vehicles built for one gauge on a line with a different gauge. A variant is the rollbock (Rollböcke in German), used under two-axle standard-gauge vehicles: each wheelset is carried on a small four-wheeled narrow-gauge trolley.[22] The entire train is converted in minutes at a slow walking pace, each rollbock being automatically matched to its wheelset from underneath.[note 4]

A further variant is "train on train", in which an entire narrow-gauge train is carried on standard-gauge flatcars on which continuous rail has been fitted.[24][25][26]

Differences in gauge are also accommodated by gauge-adjustable wheelsets, which as of 2022 were installed under some passenger vehicles on international links between Spain and France, Sweden and Finland, Poland and Lithuania, and Poland and Ukraine. In Spain, change-over facilities are extensive, since although 1668 millimetres (65.7 inches) track predominates, and high-speed lines are laid to 1435 mm (4 ft 8+12 in) standard gauge, there are many lines with narrower gauges (1000 millimetres (39 inches) and others).[27]

Dual-gauge railways by nation[edit]

Australia

AustraliaInVictoria, there are sections of 1600 mm (5 ft 3 in) and 1435 mm (4 ft 8+12 in) dual-gauge track between Southern Cross station and West Footscray, Sunshine and Newport, Albion and Jacana, North Geelong and Gheringhap, Maryborough and Dunolly, and in various goods yards and industrial sidings. Until 2008, there was a dual-gauge line between Wodonga and Bandiana.

AtAlbury railway station, New South Wales, a 1600 mm (5 ft 3 in) and 1435 mm (4 ft 8+12 in) dual-gauge line was in place until 2011. A dual-gauge line was within Tocumwal railway station until 1988, when the standard gauge component was put out of use.

In 1900, in South Australia, a three-rail dual-gauge system was proposed in order to avoid a break of gauge. However, designing turnouts was considered to be difficult due to the difference of only 165 millimetres (6.5 inches) between the 1435 mm (4 ft 8+12 in) and the 1600 mm (5 ft 3 in) broad gauge. After twenty years of discord, the proposal was abandoned.[28][29][30] Much later, the South Australian Railways successfully adopted dual-gauge turnouts.[31]

InWestern Australia, 1067 mm (3 ft 6 in) and 1435 mm (4 ft 8+12 in) of double-track dual-gauge extends for 120 km (75 mi) of the main line from East PerthtoNortham. Dual-gauge track is also used from the triangle at WoodbridgetoCockburn Junction, then to Kwinana on one branch and North Fremantle on the other. The signalling system detects the gauge of the approaching train and puts the signals to stop if the route is set for the wrong gauge.

InQueensland, there is a section of 1067 mm (3 ft 6 in) and 1435 mm (4 ft 8+12 in) dual-gauge track between the rail freight yardsatAcacia Ridge and Park Road station, which is utilised by both passenger and freight trains. Freight trains to the Port of Brisbane utilise the dual gauge Fisherman Islands line that runs parallel to the Cleveland railway line from Park Road to Lindum. Passenger trains use the dual-gauge section of the Beenleigh railway line running parallel to the electric suburban narrow gauge of the Queensland Rail city network over the Merivale Bridge into platforms 2 and 3 at Roma Street Station. This is used by standard gauge interstate New South Wales TrainLink XPT services to Sydney. In 2012, a dual-gauge line was installed between Acacia Ridge and Bromelton to serve a new freight hub at Bromelton.

The 1700 kilometres (1100 miles) long Inland Railway, under construction in 2022, will have about 300 kilometres (190 miles) of dual gauge.

Bangladesh

Bangladesh The Bangladesh Railway uses three rails to avoid breaks of gauge between its broad-gauge and metre-gauge lines. The Jamuna Bridge and Padma Bridge, which link the east–west and north–south rail systems respectively, have four-rail dual-gauge tracks. Of the 2,875 kilometres (1,786 mi) Bangladseh Railway system, about 1,600 kilometres (990 mi) has four-rail dual-gauge.[citation needed][dubiousdiscuss]

Belgium

Belgium Tram tracks in Brussels once combined 1000 mm (3 ft 3+38 in) metre gauge lines for inter-urban trams and 1435 mm (4 ft 8+12 in) lines for urban trams in a three-rail layout. In 1991, the interurban trams went out of service and then the network used only standard-gauge track.

Bulgaria

Bulgaria The Sofia tramway uses a mixture of narrow and standard gauge. A 2.6 km (1.6 mi) section of track between Krasna polyana depot and Pirotska street is dual-gauge shared by 1435 mm (4 ft 8+12 in) route 22 and 1009 mm (3 ft 3+2332 in) route 11.

Cameroon

Cameroon The new port of Kribi may serve 1000mm gauge bauxite traffic as well as 1435mm gauge iron ore traffic.

Czech Republic

Czech Republic In the Czech Republic, there is 2 km of dual gauge 1435 mm (4 ft 8+12 in) and 760 mm (2 ft 5+1516 in) track near Jindřichův Hradec. In 1985, its original four rails were converted to three rails. In 2004, in Jindřichův Hradec at a switch where a dual gauge railway bifurcates, a Junák express from PlzeňtoBrno derailed due to a signalling error. The standard gauge train had been switched on to the narrow gauge track.

France

France The Chemin de Fer de la Baie de Somme in France is dual gauge between Noyelles-sur-Mer and Saint-Valery-sur-Somme. The line has four rails with metre gauge laid within standard gauge. There are some dual-gauge (standard and Iberian) sidings at Cerbère on the Spanish border.

Germany

Germany In the 1970s, the Stuttgarter Straßenbahnen tram lines underwent a gauge conversion from 1000 mm (3 ft 3+38 in) gauge to standard gauge. This was part of an upgrade to the Stuttgart Stadtbahn. In 1981, 1435 mm (4 ft 8+12 in) and 1000 mm (3 ft 3+38 in) dual-gauge track was constructed so that new DT-8 Stadtbahn cars and old trams could share the network. In 2008, a further gauge conversion was completed. The Stuttgart Straßenbahn Museum operates 1000 mm (3 ft 3+38 in) gauge trams on weekends and special occasions.

InKrefeld on Ostwall, tram lines are dual gauge so that standard 1435 mm (4 ft 8+12 in) Rheinbahn U76 Stadtbahn cars and 1000 mm (3 ft 3+38 in) gauge trams may share the lines. At the north end of the route, at the junction with Rheinstraße, the trams reverse. There, the standard gauge line ends, while the metre gauge lines continue. At the Hauptbahnhof, on Oppumer Straße, dual gauge track continues. At the ends of Oppumer Straße, the two tracks diverge.

InMülheim there is a similar situation. The Duisburg tram line 901 meets the local line 102. The tram system in Duisburg uses 1435 mm (4 ft 8+12 in) gauge track while the tram route from Witten to Mülheim uses 1000 mm (3 ft 3+38 in) gauge tracks. Two lines share a tunnel section between the Mülheim (Ruhr) Hauptbahnhof and Schloss Broich then diverge at street level.

The tram network between WernetoBad Honnef is large with various operators and gauges. The trams in Wuppertal used 1435 mm (4 ft 8+12 in) gauge track on east–west lines and 1000 mm (3 ft 3+38 in) gauge track on north–south lines. Trams in Duisburg used 1435 mm (4 ft 8+12 in) gauge track on lines south of the Ruhr and 1000 mm (3 ft 3+38 in) gauge tracks on lines north of the Ruhr. The north lines closed in the 1960s and 1970s. Duisburg's three routes were converted to 1435 mm (4 ft 8+12 in) gauge track.

Ghana

Ghana Ghana is converting its narrow gauge to standard gauge, and is installing dual-gauge sleepers as an intermediate stage.

Greece

Greece In Greece, the line between Athens and Elefsis (now closed) was dual gauge in order to allow the 1000 mm (3 ft 3+38 in) gauge trains of the Peloponnese rail network to pass. It also allowed standard gauge trains to reach the Elefsis shipyards. In Volos, a short section of track between the main station and the harbour used an unusual triple gauge, to accommodate standard gauge trains from Larissa, metre gauge trains from Kalambaka, and the 600 mm (1 ft 11+58 in) gauge trains of the Pelion railway.

Indonesia

Indonesia In 1899, in the Dutch East Indies, dual gauge track was installed between Yogyakarta and Solo. The track was owned by the Nederlandsch-Indische Spoorweg Maatschappij, a private company, which in 1867 had built the 1435 mm (4 ft 8+12 in) gauge line. The third rail was installed to allow passengers and goods travelling over the 1067 mm (3 ft 6 in) gauge Staatsspoorweg (state railway) a direct connection. At a later date, the government constructed new tracks to allow greater capacity and higher speeds. In 1940, a third rail was installed between Solo and Gundih on the line to Semarang, allowing 1067 mm (3 ft 6 in) gauge trains to travel between Semarang, Solo and Yogyakarta via Gambringan, on the line to Surabaya instead of on the original line via Kedungjati.

In 1942 and 1943 in Java, under Japanese military occupation, conversion from took place 4 ft 8+12 in (1,435 mm) to 1067 mm (3 ft 6 in) on the Brumbung–Kedungjati–Gundih main line and the Kedungjati–Ambarawa branch line.

Until the 1970s, a short section of dual gauge 1067 mm (3 ft 6 in) and 750 mm (2 ft 5+12 in) line existed in North Sumatra on a joint line of the Deli Railway and the Atjeh Tram.

Some sugar mill railways in Java have dual-gauge sections.

Ireland

Republic of Ireland Ireland's Ulster Railway underwent a gauge conversion from 1880mm to the new Irish standard of 1600 mm (5 ft 3 in). The Dublin & Drogheda Railway underwent a gauge conversion because the gauges were too close to allow a dual-gauge line.

Italy

Italy The Potenza – Avigliano Lucania line in Italy is a dual gauge rail with 1435 mm (4 ft 8+12 in) and 950 mm (3 ft 1+38 in) tracks.

Japan

Japan In Japan, the national standard is 1067 mm (3 ft 6 in) narrow gauge. Dual gauge is used where the 1435 mm (4 ft 8+12 in) Shinkansen (bullet train) lines join the main network. For example, part of the Ōu Main Line became part of the Akita Shinkansen and was converted to dual gauge in a limited section. The longest (82.1 km (51.0 mi)) dual gauge section in Japan is near, and in, the Seikan Tunnel. Sections of the Hakone Tozan Line are among a number of other dual-gauge lines.

Mexico

Mexico Mexico previously had 1435 mm (4 ft 8+12 in) and 914 mm (ft) dual gauge track.

Netherlands

Netherlands The first railway lines in the Netherlands were constructed with a track gauge of 1945 mm (6 ft 4+916 in). For the 1939 centennial celebration, an exact replica of the country's first locomotive "De Arend" was built using the original blueprints. Since 1953, the locomotive is housed at the Dutch National Railway Museum, where in recent years, a dual-gauge track has been constructed in the rail yard, allowing for the locomotive to drive back and forth on special occasions.[32]

Poland

Poland In Poland, there is 3 kilometres (1.9 miles) of 1435 mm (4 ft 8+12 in) and 750 mm (2 ft 5+12 in) dual-gauge track in the Greater Poland Voivodeship, linking Pleszew with a nearby mainline station. It is served by narrow-gauge passenger trains and standard-gauge freight trains.

Russia

Russia Between 2008 and 2012, a 2 km (1.2 mi) dual-gauge cross-border track was rebuilt between Khasan, Russia, and Rajin, North Korea; its gauges were the Russian 1520 mm (4 ft 11+2732 in) and Korean 1435 mm (4 ft 8+12 in).[33] Similar arrangements exist on the approach to Kaliningrad, where 1435 mm (4 ft 8+12 in) track extends from the Polish border with some sections of dual gauge.

Spain

Spain In Spain, there is 21.7 km (13.5 mi) of dual gauge in the AVE line from ZaragozatoHuesca, usable for both 1435 mm (4 ft 8+12 in) standard-gauge high-speed trains and 1668 mm (5 ft 5+2132 in) Spanish network trains. Some dual-gauge sidings are at Port Bou on the French border. In 2009, Adif called for tenders for the installation of a third rail for standard-gauge trains on the 22 km (14 mi) between Castellbisbal and the Can Tunis freight terminal in Barcelona.[34]

Sweden

Sweden The bridges at the borders of Sweden and Finland, between Haparanda and Tornio have 2 km (1.2 mi) of dual gauge, 1435 mm (4 ft 8+12 in) and 1524 mm (ft) track. At each end of the dual-gauge section are yards with standard and Finnish gauge areas to allow for trans-shipment. Four rails are used because the gauges are close and the bridge structure is wider than normal to allow for the offset from the centreline of each gauge. A Rafil gauge changer is at the Tornio yard. Between Västervik and Jenny, Sweden, there is a 891 mm (2 ft 11+332 in) and 1435 mm (4 ft 8+12 in) dual-gauge line and dual-gauge track in the Västervik station area.

Switzerland

Switzerland In Switzerland, dual-gauge 1435 mm (4 ft 8+12 in) track and 1000 mm (3 ft 3+38 in) track exists between Lucerne and Horw of the Zentralbahn, between Niederbipp and Oberbipp of the Oberaargau-Jura Railways and between Chur and Domat/EmsofRhB. All three allow narrow-gauge passenger trains and standard-gauge freight trains to operate. A ″non-stop″ scheme (albeit with a pause to change locomotives) on the Montreux-Interlaken route was inaugurated in December 2022.[35] The former Zollikofen-Worblaufen-Deisswil dual gauge was cut back to Papiermühle when the factory in Deisswil closed.[when?]

Ukraine

Ukraine The railway tracks between the border with SlovakiaatSolomonovo and the border with RomaniaatNevetlenfolu are dual-gauge, 1520 mm (4 ft 11+2732 in) and 1435 mm (4 ft 8+12 in). This is in part due to the Austro-Hungarian heritage of the Zakarpattia Oblast, but also has military and political importance, as it allows standard-gauge trains to run between Romania and Slovakia by bypassing Hungary, otherwise impossible due to the break-of -gauge between the Russian-gauge network of Ukraine and standard-gauge networks of Romania and Slovakia.

United Kingdom

United Kingdom The Great Western Railway in Britain was originally built to a broad gauge of 2134 mm (7 ft 0 in), subsequently widened to 2140 mm (7 ft 012in). After a "gauge war", the gauge was convertedto1435 mm (4 ft 8+12 in). A dual-gauge system was easily installed as the gauges were well separated and the line had wooden sleepers. A short section of broad and standard gauge is at the Great Western Society site at Didcot.

The port authority in Derry, Northern Ireland, used a dual-gauge line in a street-level network to transfer freight. Two of the city's stations were on a narrow 914 mm (ft) gauge. The other two city stations were on broad 1600 mm (5 ft 3 in) gauge.

The Fairbourne RailwayinGwynedd, Wales, has a section of dual gauge track from Fairbourne station to Car Park crossing installed in the late 2010s to allow visiting 15 in (381 mm) gauge trains to run on part of the line, which was converted to 12+14 in (311 mm) gauge in 1986, usually as part of special events.

United States

United States In Los Angeles, the 1067 mm (3 ft 6 in) Los Angeles Railway and 1435 mm (4 ft 8+12 in) Pacific Electric Railway ran on dual gauge track on some downtown streets.[when?]

From 1880 to 1902, the Burlington, Cedar Rapids and Northern Railway (standard gauge) and the Burlington and Northwestern Railway (narrow gauge) shared a dual-gauge mainline from Burlington, Iowa, to Mediapolis, 23 kilometres (14 miles) to the north.

The early operational years of the State Belt RailroadinSan Francisco featured dual-gauge tracks to accommodate regional railroads of the time, which interchanged via ferry.

Until 1941, the Colorado and Southern Railway used both standard-gauge and narrow-gauge tracks, and had a dual-gauge line between Denver and Golden, Colorado.

Until the 1960s, the Denver and Rio Grande Western Railroad's Alamosa–Durango Line from Alamosa, Colorado, to Antonito was dual-gauge (914 mm (ft) and 1435 mm (4 ft 8+12 in)).

Previously, in its yard at Mount Union, Pennsylvania, the East Broad Top Railroad and Coal Company used dual-gauge tracks.

Vietnam

Vietnam In Vietnam, near the border with China, there is 1000 mm (3 ft 3+38 in) and 1435 mm (4 ft 8+12 in) dual-gauge track between Hanoi and Đồng Đăng. Other smaller dual-gauge sections exist elsewhere in the north-east of the country.[36]

See also[edit]

  • Gauntlet track
  • Glossary of rail transport terms
  • History of rail transport
  • Rail transport
  • Rail transport by country
  • Tamping machines
  • Track gauge conversion
  • Notes[edit]

    1. ^ Two-rail track on curves is re-gauged when the gauge is 20 mm over (16 mm on narrow gauge). It is sometimes done by relocating the low (inner) rail to save "spike-killing" the sleeper at the outer end, where lateral loads are greater. In other cases, the sleeper may be slid through by about 70 mm to provide "new" timber for spiking.[2] On dual-gauge turnouts, tolerances are small: only 8 millimetres (0.31 inches) over gauge and 2 millimetres (0.079 inches) under.[3]
  • ^ Port Pirie Junction was a triple-gauge station from 1937 to 1983 but, unlike Gladstone, did not have any triple-gauge track. For the most part the gauges were separate; dual-gauge tracks served a few trans-shipment sidings and another passenger station in the town's main street.[12][13]
  • ^ At that time, each transfer took 20 minutes; inspection and marshalling took up the remaining time.[20] In 1982, each of two shifts of 18 men exchanged an average of 66 bogies per day; in comparison, 100 men would have been needed to transfer the same amount of freight wagon to wagon.[21]
  • ^ The principle of attaching narrow-gauge bogies from underneath in this manner had been patented by Robert Henry Ramsey in 1872, in the United States.[23]
  • Notes to gallery photos[edit]

    1. ^ Commuter lines near Estação Central, City of Belo Horizonte, Brazil, 2007.
  • ^ Secondary main line, Wallaroo, South Australia, 2008. Such close spacing of two rails is at the limit of possibilities for three-rail dual gauge; if closer, a four-rail configuration must be built.
  • ^ Jenny, Sweden, 2006.
  • ^ Street tramway trackinLiberec, Czech Republic, 2007.
  • ^ Odawara on the Hakone Tozan Railway, Japan, 2005.
  • ^ Chemin de Fer de la Baie de Somme, France, 2007.
  • ^ Newly laid track between Mockava and Šeštokai, Lithuania, 2013 or earlier.
  • ^ Torne River rail bridge between Tornio (Finland) and Haparanda (Sweden, ahead), 2008.
  • ^ Gladstone, South Australia, early 1970s.
  • ^ Gladstone, South Australia, early 1970s.
  • ^ Gladstone, South Australia, early 1970s.
  • ^ Gladstone, South Australia, early 1970s.
  • ^ Locomotive depot, Peterborough, South Australia, 2010 (turntable was made triple-gauge in 1969 to accommodate new standard gauge).
  • ^ Gladstone railway station, 1976.
  • ^ Gladstone, South Australia, 1970s.
  • ^ Southern Cross station, Melbourne, Australia, 2010.
  • ^ National Railway Museum, Port Adelaide, 2022. Rebuilt with components from Gladstone.
  • ^ Gladstone station, South Australia, 1976. The four rails in the foreground include one rail that is common to all three gauges (the rail on the right) and the gauges are as follows (numbering rails from left to right): broad gauge, 1 and 4; standard gauge, 2 and 4; narrow gauge, 3 and 4.
  • References[edit]

    1. ^ a b Tratman, E.E. Russell (1908). Railway track and track work (3 ed.). New York: The Engineering News Publishing Co. p. 402. Retrieved 8 November 2022.
  • ^ Track Maintenance Guide. Adelaide: Australian National Railways Commission. 1988. p. section 12.2.
  • ^ "50kg dual gauge turnouts and gauge separations – construction and maintenance manual" (PDF). Australian Rail Track Corporation. 2008. Retrieved 7 November 2022.
  • ^ Rogers, K.C. (1969). Farewell narrow gauge. Adelaide: Australian Railway Historical Society (SA Division Inc.). pp. 19–22.
  • ^ Pratt, Edwin A. (1912). The state railway muddle in Australia. London: John Murray. p. 68. Retrieved 28 November 2022 – via Internet Archive.
  • ^ a b Donovan, Peter Francis; O'Neil, Bernard; Jay, Christopher (1991). The long haul: Australian National 1978–1988 (Revised ed.). Adelaide: Australian National Railways Commission. ISBN 1875359087.
  • ^ Chambers, T.F. (February 1971). "The railways and Terowie – their early history and change of pattern over nearly a century". Australian Railway Historical Society Bulletin. XXII (400): 34. ISSN 0005-0105.
  • ^ Track Maintenance Guide. Adelaide: Australian National Railways Commission. 1988. p. section 9.1.
  • ^ "Gantlet vs. gauntlet". Trains. Kalmbach Media. 1 February 2011. Retrieved 1 September 2023.
  • ^ Fitch, Ronald J. (1989). Making tracks: 46 years in Australian railways. Kenthurst NSW: Kangaroo Press. p. 141. ISBN 0864172702.
  • ^ Triple gauge at Växjö, click on Treskensspår at the left
  • ^ Bakewell, Guy; Wilson, John (September 1968). "Farewell to Ellen Street". Australian Railway Historical Society Bulletin. XIX (371): 211. ISSN 0005-0105.
  • ^ "South Australia's mixed gauge muddle" (PDF). Archived from the original (PDF) on 28 February 2016. Retrieved 8 November 2022.
  • ^ "NRM report". Catch Point Magazine. Port Adelaide: National Railway Museum. January 2022. p. 45.
  • ^ "About Steamtown". Steamtown Peterborough. Steamtown Heritage Rail Centre. 2022. Retrieved 5 November 2022.
  • ^ "The railway gauges". The Mercury (Hobart). Vol. XXI, no. 3577. (Original, Hobart. Digital reproduction, Canberra: National Library of Australia – Trove digital newspaper archive). 14 June 1872. p. 3. Retrieved 31 October 2022.
  • ^ Fitch, Ronald J. (2006). Australian Railwayman: from cadet engineer to railways commissioner. Dural, New South Wales: Rosenberg Publishing Pty Ltd. p. 168. ISBN 1877058483.
  • ^ Laird, Philip (2001). Back on track: re-thinking transport policy in Australia and New Zealand. Sydney: University of New South Wales Press. p. 187. ISBN 086840411X.
  • ^ Twain, Mark (2020). "Following the Equator". The Literature Network. Retrieved 27 May 2020.
  • ^ a b Buckland, J.L. (October 1962). "Bogie changing extends the benefits of standard-gauge". Australian Railway Historical Society Bulletin. XIII (300): 161–162. ISSN 0005-0105.
  • ^ Lee, Robert (2007). The Railways of Victoria 1854–2004. Melbourne University Publishing Ltd. p. 224. ISBN 978-0-522-85134-2.
  • ^ Harzquerbahn 2015 – Güterverkehr zwischen Unterberg und Nordhausen [Freight traffic between Unterberg and Nordhausen]. Schmalspurbahn-Fans. 2015. Retrieved 3 November 2022.
  • ^ "Ramsey's car truck shifting apparatus". Mid-Continent Railway Museum. 2007. Retrieved 3 November 2022.
  • ^ Harding, Eric (1958). Uniform railway gauge. Lothian Publishing. p. 14.
  • ^ Smith, Keith A. Tales from a Railway Odyssey. p. 114.
  • ^ Buckland, J.L. (December 1955). "The "pick-a-back" train". Australian Railway Historical Society Bulletin. VI (218): 157–162. ISSN 0005-0105.
  • ^ Álvarez, Alberto García (2010). Automatic track gauge changeover for trains in Spain (PDF) (4 ed.). Fundación de los Ferrocarriles Españoles. p. 7. ISBN 978-84-89649-56-9.
  • ^ "Personal". The Barrier Miner. Broken Hill, NSW: National Library of Australia. 3 July 1924. p. 2. Retrieved 1 September 2012.
  • ^ "Great Western Railway". The Argus. Melbourne: National Library of Australia. 11 March 1926. p. 7. Retrieved 27 August 2011.
  • ^ "Unification of gauges". The Sydney Morning Herald. National Library of Australia. 6 May 1904. p. 5. Retrieved 10 March 2014.
  • ^ Civil track engineering ARTC pdf.
  • ^ "Arend onder Stoom – Het Spoorwegmuseum". www.spoorwegmuseum.nl. Archived from the original on 26 September 2020.
  • ^ Russian Railways : Demonstration train makes run between Rajin and Khasan RZD news
  • ^ "World infrastructure market March 2009". Railway Gazette International. 14 March 2009.[permanent dead link]
  • ^ Fender, Keith (April 2023). "Swiss introduce gauge-changing train on Montreaux Interlaken route". Trains. Kalmbach Media. pp. 41–42.
  • ^ The length of Vietnam railway network Archived September 10, 2006, at the Wayback Machine
  • Further reading[edit]

    External links[edit]

    1. ^ "Diagram of mixed gauge turnouts". The Globe and Sunday Times War Pictorial. No. 272. New South Wales, Australia. 17 June 1916. p. 19 – via National Library of Australia.

    Retrieved from "https://en.wikipedia.org/w/index.php?title=Dual_gauge&oldid=1229322961"

    Category: 
    Dual gauge railways
    Hidden categories: 
    All articles with dead external links
    Articles with dead external links from February 2024
    Articles with permanently dead external links
    Webarchive template wayback links
    Articles with short description
    Short description is different from Wikidata
    Use dmy dates from November 2022
    Use Australian English from November 2022
    All Wikipedia articles written in Australian English
    All articles with vague or ambiguous time
    Vague or ambiguous time from November 2022
    Wikipedia articles needing clarification from October 2022
    Articles containing potentially dated statements from 2022
    All articles containing potentially dated statements
    Articles needing additional references from November 2022
    All articles needing additional references
    All articles with unsourced statements
    Articles with unsourced statements from March 2023
    All accuracy disputes
    Articles with disputed statements from March 2023
    Articles with GND identifiers
     



    This page was last edited on 16 June 2024, at 05:04 (UTC).

    Text is available under the Creative Commons Attribution-ShareAlike License 4.0; additional terms may apply. By using this site, you agree to the Terms of Use and Privacy Policy. Wikipedia® is a registered trademark of the Wikimedia Foundation, Inc., a non-profit organization.



    Privacy policy

    About Wikipedia

    Disclaimers

    Contact Wikipedia

    Code of Conduct

    Developers

    Statistics

    Cookie statement

    Mobile view



    Wikimedia Foundation
    Powered by MediaWiki