Line 7 of the Guangzhou Metro is a rapid transit line in Guangzhou and Foshan, Guangdong Province, China. It is envisioned as tangential line that runs across southeast Guangzhou and Foshan, allowing for orbital traffic between the suburbs of Shunde, Panyu and Huangpu to avoid the crowded stations in the city center. Line 7's color is light green.

Line 7
Train of line 7
Overview
Other name(s)M7 (plan name)
Panyu line (番禺线)
StatusOperating
OwnerCity of Guangzhou
LocaleGuangzhou (Panyu District and Huangpu District), Foshan (Shunde District)
Guangdong
Termini
  • Yanshan
  • Stations28 (including 1 complete but unopened)[a]
    Service
    TypeRapid transit
    SystemGuangzhou Metro
    Services1
    Operator(s)Guangzhou Metro Corporation
    Daily ridership163,200 (2017 daily average)[1]
    History
    OpenedDecember 28, 2016; 7 years ago (2016-12-28)
    Technical
    Line length54.24 km (33.70 mi)
    Track gauge1,435 mm (56.5 in)

    Route map

    Yanshan
    Shuixi Stabling Yard(Line 21)

    Shuixi
     21   THP1 

    Luogang
     6 

    Kefeng Lu

    Jiazhuang

    Jitang Stabling Yard

    Jitang
    Line reservation

    Dashadong
     5 

     5 
    Left arrowtoJiaokou
    toWenchong Right arrow

    Yufengwei
     13 

     13 
    Left arrowtoYuzhu
    toXinsha Right arrow

    Hongshengsha

    Changzhou
     8 

    Connection to Line 8/  8 
    Left arrowtoJiangfu
    toLianhua Right arrow

    Shenjing

    Connection to Line 4/  4 
    Left arrowtoHuangcun
    toNansha Passenger Port Right arrow

    Higher Education
    Mega Center South
     4   12 

    Higher Education Mega Center South
    Stabling Yard(Line 12)

    Lijiao Stream

    Banqiao

    Yuangang

    Nancun Wanbo
     18 

    Hanxi Changlong
     3 

    Zhongcun

    Xiecun

    Guangfo circular IR

    Shibi
     2 

    Guangzhou South Railway Station
     2   22  Foshan Metro  2 

    Foshan Metro  2  Left arrow toNanzhuang

    Dazhou Stabling Yard (Line 2)

    Dazhou Depot (Line 7)

    Dazhou

    Chengchun Stream

    Chencunbei
    Foshan Metro  11 

    Guangfo circular IR Foguan IR

    Chencun

    Jinlong

    Nanchong

    Midea

    Beijiao Park
    Foshan Metro  3 

    Foshan Metro  3  Right arrow toZhen'an

    Meidi Dadao

    Yifeng Stabling Yard
  • talk
  • edit
  • Line 7
    Simplified Chinese广州地铁7号线
    Traditional Chinese廣州地鐵7號線
    Map of Line 7 drawn to scale

    Sections

    edit

    Phase 1

    edit

    The first phase opened on December 28, 2016, and starts at Guangzhou South Railway Station and ends at Higher Education Mega Center South. It has interchanges with Line 2 at Guangzhou South Railway Station and Shibi, Line 3 at Hanxi Changlong, Line 18 at Nancun Wanbo and Line 4 at Higher Education Mega Center South and a total length is 18.6 km (11.56 mi) with 10 stations.

    Phase 1 west extension

    edit
     
    Platform of Chencun

    The plan for west extension of the first phase from Guangzhou South Railway Station to Meidi Dadao in Shunde District, Foshan was approved in October 2015.[2] The construction of the west extension to Shunde began in June 2016.[3] The west extension opened on 1 May 2022.[4][5][6] The extension is 13.447 km (8.356 mi) in length with 8 stations.[7] It has an interchange with Foshan Metro Line 3 at Beijiao Park.

    Phase 2

    edit

    The Northern extension to Yanshan opened on 28 December 2023. It extends the line into Huangpu District, having a total length of 22.2 km (13.79 mi) with 11 stations, 10 of which are operational[8] (Hongshengsha station is complete, but was not opened pending development in the area). It has interchanges with Line 13 at Yufengwei, Line 5 at Dashadong, Line 6 at Luogang and Line 21 and Huangpu Tram Line 1 at Shuixi.

    History

    edit
    Segment Commencement Length Station(s) Name
    Guangzhou South Railway Station
    — Higher Education Mega Center South
    28 December 2016 18.6 km (11.56 mi) 9 Phase 1
    Meidi Dadao
    — Guangzhou South Railway Station
    1 May 2022 13.4 km (8.33 mi)[7] 8 Phase 1 West extension
    Higher Education Mega Center South
    — Yanshan
    28 December 2023 22.2 km (13.79 mi)[8] 10 Phase 2

    Planning

    edit

    Line 7 started in 2002 as the Fangcun-Panyu-Huangpu Line which started from Xilang station on Line 1 and heads south to Panyu District. The line then roughly follows the existing first phase of Line 7 but runs slightly north, connecting to Line 2 and 3 at what today is Nanpu and Dashi Stations respectively. The line then heads east to serve and encourage development around the Xinzao and Hualong areas and cross the Pearl River to terminate at the Guangzhou Economic and Technological Development Zone,[9] which today will be served by the under construction Line 5 Phase II extension.

    Subsequently, Line 7's design was greatly revised in 2003, with the alignment east of Dashi was shifted north to Huangpu District via Shaxi, University Town and Changzhou Island. The interchange station with Line 3 was changed from Dashi to Hanxi Changlong station as constructed today. Additionally, the western terminus was changed to Guangzhou New Passenger Station, what is now Guangzhou South railway station. This shifted Line 7's plan to roughly follow what Line 7's Phase 1 and 2 are today.

    During initial planning, Line 7 considered the use of 4 car L-type light metro trains for operation. However, severe congestion issues were created after the opening of Line 3, which only uses low capacity 3 car Type B trains and Line 6 which uses even lower capacity 4 car L-shaped trains, prompted heavy public criticism. Planners subsequently reevaluated the passenger flow forecasts for the entire line of Line 7, and upgraded the design to use 6 car B-type trains. Therefore, at the time of construction of Line 7, the partly completed station structures of Line 7 platforms at Guangzhou South Railway Station and Higher Education Mega Center South station were expanded to accommodate the longer trains.

    Stations

    edit
    Station
    No.
    Station name Connections Distance
    km
    Location
    English Chinese
    7 01-8 Meidi Dadao 美的大道 - 0 Shunde
    (Foshan)
    7 01-7 Beijiao Park 北滘公园    3  2.3 2.3
    7 01-6 Midea 美的 2.2 4.5
    7 01-5 Nanchong 南涌 1.3 5.8
    7 01-4 Jinlong 锦龙 2.0 7.8
    7 01-3 Chencun 陈村 1.6 9.4
    7 01-2 Chencunbei 陈村北    11  1.5 10.9
    7 01-1 Dazhou 大洲 1.5 12.4 Panyu
    (Guangzhou)
    7 01 Guangzhou South Railway Station 广州南站  2   22     2   GZ   GSH 
      IZQ
    1.4 13.8
    7 02 Shibi 石壁  2  1.1 14.9
    7 03 Xiecun 谢村 1.9 16.8
    7 04 Zhongcun 钟村 2.2 19.0
    7 05 Hanxi Changlong 汉溪长隆  3  1.6 20.6
    7 06 Nancun Wanbo 南村万博  18  2.1 22.7
    7 07 Yuangang 员岗 2.4 25.1
    7 08 Banqiao 板桥 2.4 27.5
    7 09 Higher Education Mega Center South 大学城南  4   12  3.8 31.3
    7 10 Shenjing 深井 3.3 34.6 Huangpu
    (Guangzhou)
    7 11 Changzhou 长洲  8  2.3 36.9
    7 12 Hongshengsha[a] 洪圣沙 1.6 38.5
    7 13 Yufengwei 裕丰围  13  1.9 40.4
    7 14 Dashadong 大沙东  5  1.5 41.9
    7 15 Jitang 姬堂 2.9 44.8
    7 16 Jiazhuang 加庄 1.7 46.5
    7 17 Kefeng Lu 科丰路 1.9 48.4
    7 18 Luogang 萝岗  6 
      THP1  (OSI at Civic Square)
    2.7 51.1
    7 19 Shuixi 水西  21 
      THP1  (OSI at Shuixi Subway)
    1.3 52.4
    7 20 Yanshan 燕山 1.0 53.4

    Rolling stock

    edit

    Type B9 trains where equipped with 36.6-inch LCD displays at the end of each car and above each door.[10]

    Type Time of manufacturing Series Sets Notes
    Type B 2015–2016 B5 23 Manufactured by CRRC Guangzhou for Phase I.[11][12][13]
    Type B 2021–2022 B9 12 Manufactured by CRRC Qingdao Sifang for the Phase I West Extension.[10][14]
    Type B 2023 19 Manufactured by CRRC Zhuzhou Locomotive for Phase II.[15]

    Notes

    edit
    1. ^ a b Hongshengsha station is complete, but it is not open pending development in the area.

    References

    edit
    1. ^ 运营跃变 · 越便民 (PDF). Retrieved November 23, 2022.
  • ^ 国家发展改革委办公厅关于同意调整广州市轨道交通7号线一期工程建设方案的复函. 中华人民共和国国家发展和改革委员会 (in Chinese). 2015-10-08.
  • ^ Liu, Yong 刘勇 (2015-10-11). 未来7条地铁 无缝连通广佛. 广州乐居网 (in Chinese).[dead link]
  • ^ "【官宣来了!#七号线西延段51日开门迎客#】". weibo.com. 2022-04-30.
  • ^ 顺德落实省委"1+1+9"工作部署部分重点项目. zwgk.shunde.gov.cn (in Chinese). 2019-04-03.
  • ^ 广州市軌道交通七號線一期工程西延順德段項目環境影響報告書 (PDF).
  • ^ a b "广州地铁七号线西延顺德段工程正式开通初期运营". 2022-05-02. Archived from the original on 2022-05-02. 全长约13.447千米,总投资约99.01亿元,全线地下,共设8座车站
  • ^ a b 广州地铁 (2023-12-27). "【开通官宣:#广州两条地铁新线开通#时间敲定】". weibo.com (in Chinese). Retrieved 2023-12-28.
  • ^ "广州地铁规划方案征集市民意见". Archived from the original on 2017-04-11. Retrieved 2017-04-11.
  • ^ a b "羊城晚报-广州南站到美的大道 仅22分钟". ep.ycwb.com. Retrieved 2022-11-23.
  • ^ "南车株机获广州138辆地铁订单 首列明年11月交付" (in Chinese). 2013-11-18. Archived from the original on 2016-12-29. Retrieved 2016-12-28.
  • ^ 广州地铁 (2016-05-04). "七号线一期首批列车54日交付广州地铁调试" (in Chinese). Archived from the original on 2017-01-04. Retrieved 2016-12-28.
  • ^ 李骏; 李春明 (2015-05-20). "广州轨道交通七号线地铁车辆". 电力机车与城轨车辆. 38 (3): 11–15. doi:10.16212/j.cnki.1672-1187.2015.03.003.
  • ^ 徐振天; 梁正杰 (2022-04-26). "广州南站到美的大道 仅22分钟". 羊城晚报.
  • ^ 广州市轨道交通十一号线及十三五线路车辆监理采购项目招标公告 Archived 2021-03-29 at the Wayback Machine 廣州公共資源交易中心

  • Retrieved from "https://en.wikipedia.org/w/index.php?title=Line_7_(Guangzhou_Metro)&oldid=1221660816"
     



    Last edited on 1 May 2024, at 07:02  





    Languages

     


     / Bân-lâm-gú
    /Hak-kâ-ngî





     

    Wikipedia


    This page was last edited on 1 May 2024, at 07:02 (UTC).

    Content is available under CC BY-SA 4.0 unless otherwise noted.



    Privacy policy

    About Wikipedia

    Disclaimers

    Contact Wikipedia

    Code of Conduct

    Developers

    Statistics

    Cookie statement

    Terms of Use

    Desktop