Jump to content
 







Main menu
   


Navigation  



Main page
Contents
Current events
Random article
About Wikipedia
Contact us
Donate
 




Contribute  



Help
Learn to edit
Community portal
Recent changes
Upload file
 








Search  

































Create account

Log in
 









Create account
 Log in
 




Pages for logged out editors learn more  



Contributions
Talk
 



















Contents

   



(Top)
 


1 Route  





2 Origin & History  



2.1  Pre-Construction Phase  



2.1.1  Funding and early construction  





2.1.2  State funding  





2.1.3  Project managers  







2.2  Construction (2008-2023)  







3 References  





4 External links  














EastWest Highway (Algeria)






العربية
Deutsch
Español
Français
Nederlands

Українська
 

Edit links
 









Article
Talk
 

















Read
Edit
View history
 








Tools
   


Actions  



Read
Edit
View history
 




General  



What links here
Related changes
Upload file
Special pages
Permanent link
Page information
Cite this page
Get shortened URL
Download QR code
Wikidata item
 




Print/export  



Download as PDF
Printable version
 




Print/export  







In other projects  



Wikimedia Commons
 
















Appearance
   

 






From Wikipedia, the free encyclopedia
 


This is an old revision of this page, as edited by Real.midz (talk | contribs)at13:28, 1 May 2024 (Added more info). The present address (URL) is a permanent link to this revision, which may differ significantly from the current revision.
(diff)  Previous revision | Latest revision (diff) | Newer revision  (diff)

A1 autoroute shield}}

A1 autoroute
La vue la plus spectaculaire depuis l'autoroute Est Ouest Bouira Algérie.jpg
Route information
Length1,216 km (756 mi)
ExistedMarch 2007–present
HistoryCompleted as of August 2023; 10 months ago (August 2023)
Major junctions
East endAlgeria-Tunisia border
West endMaghnia
Location
CountryAlgeria
Major citiesConstantine, Setif, Algiers, Blida, Oran, Tlemcen, El Taref
Highway system

The East-West Highway (Arabic: الطريق السيار شرق-غرب), also referred to as the A1 Highway, is a motorway in Algeria. The project of a six-lane highway across Algeria was launched in 2007, it was finished in August 2023 after 17 years of construction [1] and is considered to be one of the largest public works projects in the world.[2]

The US$11 billion project was undertaken by a complex consortium of international suppliers, and there have been concerns about corruption and long delays.[3][4] The Central and Western sections of the road were built by a consortium of China Railway Construction Corporation and CITIC while the Eastern section was constructed by a Japanese consortium of Kajima Corporation, Nishimatsu Construction Company, Itochu Corporation, Hazama Corporation and Taisei Corporation.[5]

Route

Tunnel (2015)

The highway runs through 1,216 km (756 mi) starting from the Moroccan border and ending at the Tunisian[6] border, connecting Algeria's major coastal cities.[7] Other hub roads are under construction as well, thus providing a link to other important cities of the inner part of the country. The East-West highway was the first stage of Algeria's five-year plan, which included spending US$40.9 billion on modernization of road networks and increasing ports' capacity.

Origin & History

Pre-Construction Phase

The motorway was envisioned in the 1970s by the then planning ministry alongside other mega-projects.

Studies on the motorway began as early as 1983, analysts considered factors such as climate, topography and many socio-economic impacts on the urban centers which the motorway would pass through. Eventually, in June of 1987, the project was parliamentary approved.

Funding and early construction

In the early stages of the project, it would be funded by European, Arab and African loans.

On June 18th, 1990 the EIB (European Investment Bank) granted the first loan of 40 million euros[8] for the first section between El Affroun and Blida. A year later, in 1991, the same bank granted a 31 million euro loan for the bypass section near Bouira [9]. Between 1993-1994 a total of 100 million euros were loaned for the Lakhdaria-Bouira section of the A1 highway. The same bank continued to grant loans of up to 210 million euros up until 2002 for several portions of the highway, but there were no direct connections between these sections except for the already existing RN-4.

On October 3, 1995 , a 30 km section between El Affroun and Hoceinia ( Ain Defla ) is inaugurated. 7 years later, the Arab Fund for Economic and Social Development (FADES) granted a loan of 86 million dollars for the completion of the section, of which only 30% would be used for its implementation.[10]

Between 1996 and 2002, the African Development Bank granted a loan of $161 million for the completion of the Constantine city bypass and the 29 km section[11] between Ain Smara and El Meridj.

State funding

In February 2005 , almost a year after his re-election, Former President Abdelaziz Bouteflika announced that the financing of all of the remaining sections from the public treasury would be provided for by the government's treasury, ignoring the advice of his finance minister [12].

On July 25th, 2005 , an executive decree is published to enforce the decision and to grant the funding necessary for the remaining sections of the motorway.

The limited international call for tenders , including precise specifications due to the sheer scale of the the East-West highway project was launched on July 23, 2005 . Several responses were recorded (American, French, German and Portuguese). Ultimately, two consortia were selected: the Chinese CITIC-CRCC and the Japanese COJAAL. The results were announced on April 15th, 2006 and the production contracts were signed on September 18th in the same year.

Project managers

While the highway was owned by the state, another call for tenders was released for the management of the construction itself, the winners were as following:

Construction (2008-2023)

Although the main east-west highway project started in 2006, several sections already existed. The new sections were to be delivered scattered throughout the following decade.

The western and central sections, carried out by the Chinese group CITIC-CRCC, were inaugurated and completed during the early 2010s, but the work on the eastern section would not be completed up until 2016, which carried out by the Japanese group COJAAL. Technical problems as well as Cojaal's inability to carry out this type of infrastructure would be used to explain this delay.

A corruption scandal surfaced in 2010 , and alleged outside sources reported on the quality of the work carried out by CITIC-CRCC , and it was considered non-compliant with international standards as repair work and maintenance were already necessary as early as 2013 [13].

The project was completed on August 12th, 2023.


References

  1. ^ "Algérie: après 17 années de travaux, l'autoroute Est-Ouest est enfin terminée". RFI (in French). 2023-08-14. Retrieved 2024-05-01.
  • ^ "East-West Highway - Road Traffic Technology". Archived from the original on 8 October 2010. Retrieved 2010-11-09.
  • ^ "East-West Highway to trouble". Africa-Asia Confidential. Archived from the original on 2010-11-27. Retrieved 2010-11-09.
  • ^ "Echorouk Online - Delayed development projects cost Algeria a loss of 10.5 billion dollars". Archived from the original on 2011-07-24. Retrieved 2010-11-09.
  • ^ "East-West Highway, Algeria". Road Traffic Technology.
  • ^ "El Tarf: the opening of the section of the East-West highway and its fruitful socio-economic impact".
  • ^ "Construction of East West Highway in Algeria". 2010-11-09. Archived from the original on 2010-10-02. Retrieved 2010-11-09.
  • ^ "AUTOROUTE EST-OUEST". archive.wikiwix.com. Retrieved 2024-05-01.
  • ^ "AUTOROUTE EST-OUEST II (BOUIRA)". archive.wikiwix.com. Retrieved 2024-05-01.
  • ^ "Implementing Health Reform: A January Exchange Enrollment Report (Page 80)". Forefront Group. 2014-02-13. Retrieved 2024-05-01.
  • ^ "Presidential Decree n o 03-328 of October 6, 2003 MINISTRY OF FINANCE JO N o 60 of October 8, 2003, Page 4 Approving loan agreement No. 2000 110000013 signed on June 2, 2003 in Addis Ababa between the People's Democratic Republic of Algeria and the African Development Bank for the financing of the motorway bypass project of Constantine - Phase II (Aïn El Bey section - CW 133)" (PDF).
  • ^ Excerpt, "He announces, after listening to one point of the situation, his decision to have the entire remaining 900 km of the East-West highway financed by the Public Treasury" - Abdelatif Benachenhou - "Return to a broken destiny" - El Kadi Ihsane - in El Watan on 05-09-2005
  • ^ "Ali Idir, "Delivery of the entire East-West highway not before 2016"". Retrieved 2013-09-05.{{cite web}}: CS1 maint: url-status (link)
  • External links


  • t
  • e

  • Retrieved from "https://en.wikipedia.org/w/index.php?title=East–West_Highway_(Algeria)&oldid=1221695839"

    Categories: 
    Highways in Algeria
    Transport in Algeria
    Algerian transport stubs
    Africa road stubs
    Hidden categories: 
    CS1 French-language sources (fr)
    CS1 maint: url-status
    Articles with short description
    Short description matches Wikidata
    Infobox road maps for Wikidata migration
    Infobox road instances in Algeria
    Articles containing Arabic-language text
    All stub articles
     



    This page was last edited on 1 May 2024, at 13:28 (UTC).

    This version of the page has been revised. Besides normal editing, the reason for revision may have been that this version contains factual inaccuracies, vandalism, or material not compatible with the Creative Commons Attribution-ShareAlike License.



    Privacy policy

    About Wikipedia

    Disclaimers

    Contact Wikipedia

    Code of Conduct

    Developers

    Statistics

    Cookie statement

    Mobile view



    Wikimedia Foundation
    Powered by MediaWiki