1 2015 plans  



1.1  Core section  





1.2  Northern Regional section  





1.3  Potential eastern extension  





1.4  South West section  







2 Transport for London consultations  



2.1  2013 consultation  





2.2  2014 consultation  





2.3  2015 consultation  







3 Cost and funding  





4 History  



4.1  1970s  





4.2  1980s  





4.3  1990s  





4.4  2000s  





4.5  2010s  



4.5.1  2008 safeguarded route  





4.5.2  Northern and southern destinations  









5 Support and opposition  



5.1  Support  





5.2  Opposition  







6 Naming  





7 See also  





8 References  





9 External links  














Crossrail 2






Català
Deutsch
Français
Português
Simple English

 

Edit links
 









Article
Talk
 

















Read
Edit
View history
 








Tools
   


Actions  



Read
Edit
View history
 




General  



What links here
Related changes
Upload file
Special pages
Permanent link
Page information
Cite this page
Get shortened URL
Download QR code
Wikidata item
 




Print/export  



Download as PDF
Printable version
 




In other projects  



Wikimedia Commons
 
















Appearance
   

 






From Wikipedia, the free encyclopedia
 


Crossrail 2
Overview
StatusProposed, consultation and design paused since 2020
Owner
  • Network Rail
  • Stations47
    Websitecrossrail2.co.uk Edit this at Wikidata
    Service
    TypeCommuter/suburban rail
    Rapid transit
    SystemNational Rail
    Technical
    Number of tracks2
    Track gauge1,435 mm (4 ft 8+12 in) standard gauge

    Route map

    Map of the proposed Crossrail2 routes

    Crossrail 2 is a suspended proposal for a hybrid commuter rail and rapid transit route in South East England, running from nine stations in Surrey to three in Hertfordshire, providing a new North–South rail link across Greater London. It would connect the South West Main Line to the West Anglia Main Line, via Victoria and King's Cross St Pancras. The intent was to alleviate severe overcrowding that would otherwise occur on commuter rail routes into Central London.[1][2] When first proposed, the hope was for construction to start around 2023, with the new line opening from the early 2030s.[3] The project's cost has been estimated at £31.2 billion.[4]

    The line would have been the fourth major rail project in the capital since 2000 (East London line extensions opened in May 2010, the Thameslink Programme opened in 2018 and Crossrail opened in May 2022). National Rail's projections of overcrowding, including in suburbs and tourist destinations less well-served by the Underground, led it to call for more new lines[5] and cross-London line proposals gained more importance with Euston being named as the terminus of the planned High Speed 2 rail line.[6]

    The scheme was shelved as part of the conditions for emergency COVID-19 funding worth £1.8 billion between the government and Transport for London (TfL) announced on 1 November 2020.[7]

    The project was earlier known as the Chelsea–Hackney line (orChelney line) in reference to a potential route. The plan for a line on this alignment has existed in various forms since 1970, initially as an Underground service and later as a standard railway.

    2015 plans

    [edit]
  • t
  • e
  • Crossrail 2

    2015 Consultation Route [8]

    Broxbourne National Rail

    Cheshunt National Rail London Overground

    Waltham Cross

    Enfield Lock

    Brimsdown

    Ponders End

    Meridian Water

    Northumberland Park

    Tottenham Hale National Rail Victoria Line

    Oakleigh Road depot

    National Rail New Southgate

    National Rail Alexandra Palace
    Piccadilly Line Turnpike Lane

    or Piccadilly Line Wood Green

    London Overground Victoria Line National Rail Seven Sisters

    future Eastern Branch
    East London line Dalston

    Hackney Central London Overground

    Angel Northern Line

    Euston St. Pancras
    National Rail Thameslink London Overground Eurostar
    Circle line (London Underground) Hammersmith & City Line Metropolitan Line Northern Line Piccadilly Line Victoria Line

    Tottenham Court Road Elizabeth line Central line (London Underground) Northern Line

    Victoria National Rail Circle line (London Underground) District Line Victoria Line

    King's Road Chelsea

    Clapham Junction National Rail London Overground

    either
    Northern Line National Rail Balham

    or
    Tooting Broadway Northern Line

    Weir Road depot

    Wimbledon National Rail Thameslink District Line Tramlink

    Raynes Park National Rail

    Motspur Park National Rail
    National Rail New Malden

    Malden Manor

    Tolworth

    Chessington North

    Chessington South
    Berrylands

    Worcester Park
    National Rail Surbiton

    Greater London boundary
    Greater London boundary

    Stoneleigh
    Thames Ditton

    Ewell West
    Hampton Court

    Epsom National Rail
    Norbiton

    National Rail Kingston

    Hampton Wick

    National Rail Teddington

    Fulwell

    Hampton

    Greater London boundary
    Kempton Park

    Sunbury

    Upper Halliford

    Shepperton

    This route is from the 2015 public consultation.[9]

    Core section

    [edit]

    Operating in new tunnels at 30 trains per hour (in each direction):

    Also in new tunnels, connected to a junction north of Dalston, at 10 and 15 trains per hour:

    Northern Regional section

    [edit]

    Running at between 10 and 15 trains per hour[14] on new rails above ground, connected to a junction north of Dalston:

    Tottenham Hale Victoria Line National Rail (West Anglia Main Line, Lea Valley lines) all stations[15]toBroxbourne for Crossrail 2 services[16] and Cheshunt National Rail.

    Potential eastern extension

    [edit]

    The 2015 consultation earmarks a "potential future Eastern Branch"[17]

    South West section

    [edit]

    Above ground, after surfacing south of Wimbledon station, using the existing SWML slow line, and providing between 4 and 20 trains per hour, the southern section comprises:

    Transport for London consultations

    [edit]

    2013 consultation

    [edit]

    In May 2013, TfL began public consultation on two potential options:

    The results of the consultation were published on 29 November 2013 by TfL and revealed broad support for the Crossrail 2 plans. 96% of respondents supported or strongly supported the plans, whilst 2% opposed or strongly opposed them. The regional route had greater support than the metro route, with 84% of respondents supporting or strongly supporting the regional route versus 73% for the metro plans.[23]

    The greatest level of opposition to the principle of Crossrail 2 came from the residents of Kensington and Chelsea, the only area with more than 5% of respondents (16%) who strongly opposed the scheme. Nearly 20% of respondents from this area either opposed or strongly opposed the scheme; the corresponding percentages in all other areas did not exceed 10%.[24]

    2014 consultation

    [edit]

    In June 2014, a consultation began on small modifications to the 2013 proposals. The changes proposed fell broadly into three areas: extending the Alexandra Palace branch to New Southgate; relocation or removal of the Chelsea station; and moving the point at which the two northern branches diverged to beyond either Dalston Junction or Hackney Downs station, calling at only one of these two stations.[25]

    2015 consultation

    [edit]

    A further consultation began in October 2015.[26] In October 2015, the route proposal was changed in three ways:

    In January 2015, Surrey County Council published a detailed report lobbying for TfL to consider extending branches to Dorking and Woking.[28]

    Cost and funding

    [edit]

    The cost of the scheme has been estimated at £27–32 billion, in 2014 prices including the cost of new trains and Network Rail works.[29] However Transport for London (TfL) argued the full cost of the project could be £45 billion in 2017. To ease the funding issues TfL recommended spreading the funding over a longer period and completing the project by the 2040s, ten years after the initial projection.[30]

    In the 2016 Budget, the Treasury gave the green light for the project, and allocated £80 million towards developing the project, with the aim of bringing forward a Hybrid Bill "this Parliament", meaning before 2020.[31]

    In the 2017 Autumn Budget, the Treasury said only that it will "continue to work with Transport for London on developing fair and affordable plans for Crossrail 2, including through an independent review of funding and financing".[32] On 2 March 2018, the UK's Transport Secretary, who represents a seat centred on a prospective terminus of one of the branch lines (Epsom and Ewell), announced Mike Gerrard would lead the Treasury's required Independent Affordability Review, which is expected to conclude in the summer of 2018.[33]

    The Mayor of London intends to charge Mayoral Community Infrastructure Levy in the same manner as for the original Crossrail project.[34]

    The funding plan for building Crossrail 2 was postponed as part of the £1.8 billion COVID-19 pandemic financial recovery plan agreed by the government and TfL, which also required the option for driverless Crossrail 2 trains to be further investigated. Most consultancy work will be brought to an orderly end, though land for the project will be safeguarded.[7]

    History

    [edit]

    A south-west/north-east tube line was originally planned as early as 1901[35] and a Bill was put before Parliament in 1904.[36] However, political manoeuvring by rival tube magnate Charles Yerkes ended the proposal.[35]

    1970s

    [edit]

    A south-west to north-east tube line was proposed in 1970 by the London Transport Board's London Rail Study as the next project after the completion of the Victoria line and the Fleet line (now the Jubilee line). Designed to relieve pressure on the District, Central and Victoria lines and to link two areas without tube services, the route would have taken over the Wimbledon branch of the District as far as Parsons Green, then followed a new underground alignment via Aldwych (where it would take over the then Piccadilly line shuttle to Holborn); thence to Leytonstone, and continuing over one of the branches of the Central line.[37] For financial reasons the line was not built, but the idea has remained.

    1980s

    [edit]

    Following the Central London Rail Study of 1989, a route through central London was safeguarded.[35] As the route would serve both King's Cross and King's Road it was suggested that it could be named Kings line. It was decided, however, that the Jubilee line extension should take priority and the project was postponed.

    1990s

    [edit]

    In 1995, an alternative Express Metro plan was put forward that would utilise more existing track, have fewer stations and be built to National Rail standards. It would take one of three routes from East Putney on the District linetoVictoria; either Putney Bridge, Parsons Green and Chelsea or King's Road as in the original safeguarded plan; or to Wandsworth Town and Clapham Junction and then via Chelsea Harbour and King's Road or via Battersea. From Hackney Central it would split into two branches, to Leytonstone and then on to Epping taking over the Central line; and taking over the North London LinetoWoolwich,[35] a route now followed by the Docklands Light Railway.

    The 1991 safeguarding also included a spur south of Victoria across the river to Battersea Park, for stabling trains and to access a riverside tunnelling site.

    2000s

    [edit]

    The London East West Study in 2000 considered Crossrail, the Chelsea–Hackney line and a combination of the two, from WimbledontoTottenham Court Road and then to Liverpool Street. The Study supposes main-line gauge, and would omit a station at Piccadilly Circus. Its version of the Chelsea-Hackney Regional Metro splits in the north, with one branch via Dalston taking over the Epping branch of the Central line, the other to Finsbury Park, then using the disused alignment of the Northern Heights plan, taking over the High Barnet branch of the Northern line. The Express Metro option would run on the East Coast Main Line.[35][38]

    Crossrail was given the go-ahead in 2007 in preference to the Chelsea–Hackney line, despite some commentators favouring the latter[39] putting implementation after Crossrail's completion date of 2018. The Chelsea–Hackney plans were taken over by Crossrail as Crossrail 2.

    In 2007, the 1991 route was updated – Sloane Square was dropped and the Central line's Epping branch from Leytonstone was re-safeguarded.[36] Due to objections from residents of Sloane Square, it was reinstated the following year.[40][41] South West Trains' Wimbledon depot was safeguarded as a depot for the line.[41] The safeguarding was enlarged from tube gauge to Network Rail loading gauge as it became clear that larger and longer trains would be needed.[42] Of the three routes proposed for south-west London the Royal Borough of Kensington and Chelsea initially favoured one going south via Imperial Wharf to Clapham Junction, but now supports the takeover of the District line's Wimbledon branch.[43] Under these present plans, only one entirely new station would be constructed, at Chelsea.

    2010s

    [edit]

    2008 safeguarded route

    [edit]

    A route for the line was safeguarded (legally protected from conflicting development) in 2008. It linked the District line's Wimbledon branch with the Central line's Epping branch via Parsons Green, Chelsea, Sloane Square, Victoria, Piccadilly Circus, Tottenham Court Road, King's Cross St Pancras, Angel, Essex Road, Dalston Junction, Hackney Central, Homerton and Leytonstone.[40][44] The safeguarding also includes a spur from Victoria under the ThamestoBattersea Park for stabling and access to a tunnelling site.[40][41] The safeguarded route was reviewed by the Department for Transport in 2013.[2]

    Northern and southern destinations

    [edit]

    Network Rail's July 2011 route utilisation strategy (RUS) for London and the South East supports the existing safeguarded route but speculates about possible modifications in addition to re-routing via Euston. To the south, it suggests that the tunnels should go from Victoria via Clapham Junction to beyond Wimbledon, instead of surfacing near Parsons Green and taking over the District line from there to Wimbledon. To the north, it suggests that the West Anglia corridor would be a better destination than a branch of the Central line. These suggestions are driven by what the RUS sees as the need for extra capacity on the South West Main Line and the West Anglia corridor. With the planned terminus of HS2atEuston, Chelsea–Hackney was put back to the top of the agenda for new lines, diverted via Euston.

    The London and South East second generation RUS by Network Rail proposed some changes to the safeguarded route: serving Clapham Junction rather than the Wimbledon branch of the District line, not serving Sloane Square, and serving Euston as well as King's Cross St Pancras. The RUS was also open to changes north of Hackney Central and branches south of Clapham Junction, both of which were seen as later phases.[45]

    TfL responded by releasing its preferred options – an automatic metro and a regional scheme:[46]

    In July 2015, Surrey County Council commissioned a study to propose in detail and with cost-benefits analysed proposals, services from Surbiton as far as the main line stop of Woking (and whether or not to serve directly the four main intervening stations).[47] Options explored were the re-routing trains so as not to terminate at Waterloo and creative timetabling plans to add capacity to the South West Main Line such as the option of moving trains onto the lighter-used New Guildford Line which runs between Surbiton and Guildford, looking at more semi-fast stopping patterns enabled as well once the Waterloo bottleneck is lifted.[47]

    Automatic Metro

    Regional Option

    Both TfL routes at both ends of the route serve Clapham Junction to a higher level than relieving the District line, and the Victoria line at its northern end, and the Central line. The regional option relieves the South West Main Line, and congested sections of the Northern line and Piccadilly line, by creating alternative routes for journeys from outside Zones 1 and 2.

    In February 2013, business group London First's Crossrail taskforce, chaired by former Secretary of State for Transport Andrew Adonis published its recommendations for Crossrail 2, favouring the regional option.[48] Later the same day, Network Rail endorsed the plans.[49]

    On 5 February 2015 Dr Michèle Dix was appointed managing director of Crossrail 2.[50]

    Proposed changes from previous plans were:

    In March 2016, the National Infrastructure Commission said that Crossrail 2 should be taken forward "as a priority" and recommended that a bill should pass through Parliament by 2019 with the line opening by 2033.[51]

    Support and opposition

    [edit]
    Curzon Soho

    Support

    [edit]

    Boris Johnson, Mayor of London in 2013, said at that time: "The key question now is not whether Crossrail 2 should happen, but how quickly we can get it built".[52] Johnson, as Prime Minister, restated his backing for the project at an event to mark the opening of the Elizabeth Line in May 2022.[53][54]

    The current Mayor of London, Sadiq Khan, also supports the proposal,[55] as does the former Secretary of State for Transport Chris Grayling.[4]

    Many local authorities in South-east England and London released a letter on 13 April 2017, expressing their support for Crossrail 2.[56] ITV news reported in April 2017 that "dozens of MPs" supported Crossrail 2.[57]

    After TfL conducted a public consultation in 2017, it was reported by the Fitzrovia Partnership that 96% of respondents supported Crossrail 2 and 80% of respondents preferred the broader of the two options, the Regional option.[58]

    The London Chamber of Commerce announced its support in July 2017 with the Greater Manchester Chamber of Commerce announcing support for Crossrail 2 in September 2017.[59][60]

    During the Elizabeth line opening ceremony in May 2022, Boris Johnson said that "the government should be 'getting on with' building Crossrail 2", however he also clarified that the business case will need to be written and put forward by Transport for London.[61][62]

    Opposition

    [edit]

    In 2014, Transport for London announced that the site of the art-house Curzon cinema in Soho had been identified as an area that "may be required to enable the construction of a Crossrail 2 ticket hall" and that "plans for the above site redevelopment may include a replacement cinema".[63] In 2015, the chairman of the "Save Soho" campaign group called the development "deeply worrying".[64]

    The plans for Wimbledon station involve the redevelopment of parts of Wimbledon town centre, including the Centre Court shopping centre.[65] Merton Council issued a seven-page cross-party objection to the plans.[66]

    There was only a short interval between the announcements of the confirmation of continued government support for Crossrail 2 in 2017, and of the scaling back of proposed railway electrification projects which would particularly benefit Wales and Northern England. Money has been earmarked in the longer term to match London's large forecast population growth. All such forecasts rely on assumptions in terms of where people will wish to live, jobs will be created and housing targets have been set accordingly for 2015–2030,[67][68][69] in contrast to the low growth forecast for the rest of England, all of which could be altered by government policy. Greater Manchester mayor Andy Burnham considered that the in-principle spending decision gives undue and unbalanced priority to London and South East England over other parts of the United Kingdom.[70]

    Naming

    [edit]

    Between the 1970s and 1990s, proposals were known as the 'Chelsea-Hackney line' due to the destinations served. The proposed line gained the nickname 'Chelney', following the portmanteau example of the Bakerloo line.

    In the 2000s, the project became 'Crossrail 2' in light of the east-west Crossrail project. In 2014, Mayor of London Boris Johnson called for the future line to be called the "Churchill line", after Winston Churchill.[71]

    See also

    [edit]

    References

    [edit]
    1. ^ Edwards, Tom (5 February 2013). "Crossrail 2 stations proposed by London business leaders". BBC News. Retrieved 8 March 2013.
  • ^ a b "Crossrail 2: Supporting London's Growth" (PDF). London First. February 2013. Archived from the original (PDF) on 13 February 2013. Retrieved 18 February 2013.
  • ^ "Next steps". Crossrail 2.
  • ^ a b Gwyn Topham (24 July 2017). "Transport secretary's backing for Crossrail 2 sparks anger outside London". The Guardian. Retrieved 26 July 2017.
  • ^ New lines 'may be needed to beat train overcrowding'[dead link] Press Association
  • ^ "HS2 fuels Crossrail 2 business case". Transport News – Publications > Local Transport Today. 21 December 2010. Retrieved 30 March 2018.
  • ^ a b Topham, Gwyn. "Crossrail 2 plans shelved as part of £1.8bn TfL funding deal". The Guardian. Retrieved 2 November 2020.
  • ^ "Citizen Space - Crossrail 2 - October 2015". Retrieved 22 November 2015.
  • ^ "Citizen Space – Crossrail 2 – October 2015". Archived from the original on 1 August 2017. Retrieved 22 November 2015.
  • ^ "Clarification information Tooting and Balham: S12B" (PDF). Archived from the original (PDF) on 22 November 2015. Retrieved 21 November 2015.
  • ^ "Crossrail 2 factsheet: Seven Sisters station" (PDF). Archived from the original (PDF) on 29 July 2020. Retrieved 23 November 2015.
  • ^ a b "Crossrail 2 factsheet: Seven Sisters to New Southgate Route Options" (PDF). Archived from the original (PDF) on 26 February 2021. Retrieved 21 November 2015.
  • ^ "Crossrail 2 train maintenance depots and stabling" (PDF). Retrieved 23 November 2015.
  • ^ "Crossrail 2 factsheet: Services at Broxbourne, Cheshunt and Waltham Cross" (PDF). Archived from the original (PDF) on 5 March 2016. Retrieved 23 November 2015.
  • ^ "Crossrail 2 factsheet: Services between Enfield Lock and Tottenham Hale" (PDF). Retrieved 23 November 2015.
  • ^ "The Transport Committee: Crossrail and the Overground Talk Shop". London Reconnections. 7 March 2013. Retrieved 7 March 2013.
  • ^ "Crossrail 2 route". Retrieved 21 November 2015.
  • ^ "Crossrail 2 factsheet: Services at New Malden, Motspur Park and Raynes Park" (PDF). Retrieved 23 November 2015.
  • ^ "Crossrail 2 factsheet: Services between Malden Manor and Chessington South" (PDF). Retrieved 23 November 2015.
  • ^ "Crossrail 2 factsheet: Services between Worcester Park and Epsom" (PDF). Archived from the original (PDF) on 17 November 2015. Retrieved 23 November 2015.
  • ^ "Crossrail 2 factsheet: Services between Berrylands and Hampton Court" (PDF). Archived from the original (PDF) on 23 November 2015. Retrieved 23 November 2015.
  • ^ "Crossrail 2 factsheet: Services between Norbiton, Kingston and Shepperton" (PDF). Retrieved 23 November 2015.
  • ^ Steer Davies Gleave (October 2013). "Crossrail 2 Consultation Report" (PDF). Transport for London Website. p. 1. Retrieved 29 November 2013.
  • ^ Steer Davies Gleave (October 2013). "Crossrail 2 Consultation Report" (PDF). Transport for London Website. p. 18. Retrieved 29 November 2013.
  • ^ "Crossrail 2 June 2014". TfL Consultations Portal. Transport for London. Archived from the original on 4 August 2017. Retrieved 5 July 2014.
  • ^ "Public consultation begins on 'transformative' Crossrail 2".[permanent dead link]
  • ^ "Crossrail October 2015". Archived from the original on 1 August 2017. Retrieved 30 October 2015.
  • ^ "Consultation report recommends Crossrail could extend to Dorking". January 2015.[permanent dead link]
  • ^ "Funding – Crossrail 2".
  • ^ Jonathan Prynn (3 October 2017). "Alarm as Crossrail 2 'may not be completed until the 2040s'". Evening Standard. Retrieved 12 October 2017.
  • ^ Budget 2016, HM Treasury, 16 March 2016
  • ^ Autumn Budget 2017, HM Treasury, 22 November 2017
  • ^ Grayling: progress on Transpennine route upgrade and Crossrail 2 to advance in lockstep, Department for Transport, 2 March 2018
  • ^ "Mayoral Community Infrastructure Levy". Mayor of London. Retrieved 5 August 2021.
  • ^ a b c d e Feather, Clive. "Technical information about the Chelsea-Hackney Line". Retrieved 7 March 2008.
  • ^ a b "Consultation on safeguarding revision for the Chelsea-Hackney line". Department for Transport. Retrieved 18 October 2007.
  • ^ "London Transport plans third new Tube Line". The Times. UK. 2 January 1970.
  • ^ "London East West Study" (PDF). Shadow Strategic Rail Authority. 2000. Archived from the original (PDF) on 13 October 2007.
  • ^ "Crossrail will eat money. Kill it, Boris, and save the bankrupt Tube instead". Evening Standard. Archived from the original on 18 October 2012. Retrieved 30 September 2015.
  • ^ a b c Chelsea–Hackney Line Safeguarding Directions, June 2008 Part A (PDF), Crossrail, accessed 22 December 2010
  • ^ a b c Consultation on safeguarding revision of the Chelsea Hackney Line – outcome report, Department for Transport
  • ^ Trouble Up The (Dalston) Junction – The Difficulties of Safeguarding, London Reconnections
  • ^ "Chelsea-Hackney Line: first on the agenda". Royal Borough of Kensington and Chelsea. October 2003. Retrieved 18 October 2007.
  • ^ Chelsea–Hackney Line Safeguarding Directions, June 2008 Part B (PDF), Crossrail, accessed 22 December 2010
  • ^ "London and South East Route Utilisation Strategy (section 8.5)" (PDF). Network Rail. July 2011. Archived from the original (PDF) on 13 December 2013. Retrieved 11 February 2012.
  • ^ "Metro or regional rail? TfL maps Crossrail 2 options". TransportXtra. 18 November 2011. Retrieved 11 February 2012.
  • ^ a b "Crossrail 2 project could include Woking and Guildford stations". 96.4 Eagle Radio. Archived from the original on 20 July 2015. Retrieved 17 July 2015.
  • ^ "Crossrail 2 supporting London's growth: Final report of London's first Crossrail task force" (PDF). londonfirst.co.uk. Archived from the original (PDF) on 19 October 2016. Retrieved 16 April 2017.
  • ^ "Crossrail 2 supporting London's growth: Final report of London's first Crossrail task force". lbreakingtravelnews.com. Retrieved 16 April 2017.
  • ^ "Michèle Dix takes over as Crossrail 2 chief, receives CBE". Union Internationale des Transports Publics. Archived from the original on 7 November 2017. Retrieved 1 November 2017.
  • ^ "Crossrail 2 must be developed 'as a priority' and delivered by 2033 – NIC".
  • ^ Beard, Matthew (29 November 2013). "Huge support for Mayor's £12bn Crossrail 2 scheme for London". London Evening Standard. p. 6.
  • ^ Hakimian, Rob (18 May 2022). "Boris Johnson says it's now time to build Crossrail 2". New Civil Engineer. Retrieved 24 May 2022.
  • ^ "Let's 'crack on' with Crossrail 2, urges PM as Elizabeth Line completes". ITV News. 17 May 2022. Retrieved 24 May 2022.
  • ^ "'Crossrail 2 vital to support London's growth', says Mayor". London. 28 October 2014. Retrieved 16 April 2016.
  • ^ "Councils unite to call on government for Crossrail 2 backing". London.gov.uk. 13 April 2017. Retrieved 12 February 2018.
  • ^ "Dozens of MPs urge the Government to support Crossrail 2". ITV News. 21 April 2017. Retrieved 12 February 2018.
  • ^ "crossrail-2 announced and out for consultation". FitzroviaPartnership. 29 June 2017. Retrieved 12 February 2018.
  • ^ Rebecca Smith (24 July 2017). "Crossrail 2 latest: Mayor Sadiq Khan and transport secretary Chris Grayling set out next steps for £31bn rail route". City AM. Archived from the original on 13 February 2018. Retrieved 12 February 2018.
  • ^ "Chamber Supports Calls for Crossrail 2". BBP media. 14 September 2017. Retrieved 12 February 2018.
  • ^ Hakimian, Rob (18 May 2022). "Boris Johnson says it's now time to build Crossrail 2". New Civil Engineer. Retrieved 26 May 2022.
  • ^ Lancefield, Neil (17 May 2022). "PM says 'we should be getting on' with Crossrail 2". Evening Standard. Retrieved 26 May 2022.
  • ^ Brown, Kat (30 December 2014). "Curzon Soho cinema faces demolition for Crossrail". The Daily Telegraph. London. Retrieved 1 October 2015.
  • ^ Topham, Gwyn (22 September 2015). "Celebrities join fight to save Soho's Curzon cinema from Crossrail 2". The Guardian. London. Retrieved 1 October 2015.
  • ^ "Crossrail 2 consultation has ended: here is what has been said so far". Wimbledon Guardian. 8 January 2016.
  • ^ "CROSSRAIL 2 CONSULTATION: MERTON COUNCIL'S CROSS-PARTY RESPONSE" (PDF). Archived from the original (PDF) on 27 March 2016. Retrieved 16 September 2016.
  • ^ Cambridge Econometrics (March 2017). "Economic and Demographic Scenarios for London in 2030" (PDF). King's College London. Archived from the original (PDF) on 13 June 2018.
  • ^ Tovey, Alan (8 December 2015). "London to outpace New York as City drives growth" – via www.telegraph.co.uk.
  • ^ Hill, Dave (9 January 2015). "London's booming: how the city's population surged past pre-war peak". The Guardian – via www.theguardian.com.
  • ^ "Crossrail 2: Support by government 'outrageous' after northern snub". BBC. 25 July 2017. Retrieved 12 October 2017.
  • ^ Collins, Nick (28 October 2014). "Boris Johnson says Crossrail Two better for economy than HS2". Daily Telegraph. ISSN 0307-1235. Retrieved 20 August 2019.
  • [edit]
    Retrieved from "https://en.wikipedia.org/w/index.php?title=Crossrail_2&oldid=1227756185"

    Categories: 
    Proposed railway lines in London
    Transport in Epping Forest District
    Proposed London Underground lines
    Underground commuter rail
    Hidden categories: 
    All articles with dead external links
    Articles with dead external links from June 2024
    Articles with dead external links from December 2017
    Articles with permanently dead external links
    Articles with dead external links from February 2018
    Articles with short description
    Short description is different from Wikidata
    Wikipedia articles in need of updating from December 2022
    All Wikipedia articles in need of updating
    Use dmy dates from March 2020
    Use British English from November 2015
    Articles needing additional references from November 2015
    All articles needing additional references
    Pages using BSto or BSsrws with missing text values
    Commons category link from Wikidata
     



    This page was last edited on 7 June 2024, at 16:47 (UTC).

    Text is available under the Creative Commons Attribution-ShareAlike License 4.0; additional terms may apply. By using this site, you agree to the Terms of Use and Privacy Policy. Wikipedia® is a registered trademark of the Wikimedia Foundation, Inc., a non-profit organization.



    Privacy policy

    About Wikipedia

    Disclaimers

    Contact Wikipedia

    Code of Conduct

    Developers

    Statistics

    Cookie statement

    Mobile view



    Wikimedia Foundation
    Powered by MediaWiki