Jump to content
 







Main menu
   


Navigation  



Main page
Contents
Current events
Random article
About Wikipedia
Contact us
Donate
 




Contribute  



Help
Learn to edit
Community portal
Recent changes
Upload file
 








Search  

































Create account

Log in
 









Create account
 Log in
 




Pages for logged out editors learn more  



Contributions
Talk
 



















Contents

   



(Top)
 


1 Route  





2 Purpose  





3 Project development  





4 Usage  





5 See also  





6 References  





7 External links  














Gas Interconnector GreeceBulgaria






Azərbaycanca
Български
Ελληνικά
فارسی
Français
Italiano
Русский
Українська
Tiếng Vit
 

Edit links
 









Article
Talk
 

















Read
Edit
View history
 








Tools
   


Actions  



Read
Edit
View history
 




General  



What links here
Related changes
Upload file
Special pages
Permanent link
Page information
Cite this page
Get shortened URL
Download QR code
Wikidata item
 




Print/export  



Download as PDF
Printable version
 
















Appearance
   

 






From Wikipedia, the free encyclopedia
 


Interconnector Greece–Bulgaria
Location
CountryGreece
Bulgaria
General directionSouth–North
FromKomotini, Greece
Passes throughKardjali, Haskovo, Dimitrovgrad, Bulgaria
ToStara Zagora, Bulgaria
General information
TypeNatural gas
PartnersBulgarian Energy Holding
IGI Poseidon (DEPA & Edison S.p.A.)
OperatorICGB AD
Commissioned2022
Technical information
Length182 km (113 mi)
Maximum discharge3 billion cubic metres per annum (110×10^9 cu ft/a)
Diameter32 in (813 mm)
Websitewww.icgb.eu Edit this at Wikidata

Gas Interconnector Greece–Bulgaria is a natural gas pipeline from the Greek to the Bulgarian natural gas pipeline network.[1][2] It became operational on 1 October 2022.[3]

Route[edit]

On 14 July 2009, Bulgarian Energy Holding signed an agreement with DEPA and Edison S.p.A. on setting up a company to construct and operate the branch pipeline Interconnector Greece-Bulgaria with a capacity of one billion cubic meters of gas per year.[4] The pipeline will be 160 kilometres (99 mi) between Komotini and Stara Zagora in Bulgaria.[4]

The capacity of the pipeline is to be 3 to 5 billion cubic metres per annum (110 to 180 billion cubic feet per annum) with reverse flow capability. The connecting points are to be Komotini, Greece and Stara Zagora, Bulgaria.[needs update] The length of the pipeline is about 150 kilometres (93 mi) in Bulgaria and 30 kilometres (19 mi) in Greece. The pipe diameter is 813 millimetres (32.0 in), with an estimated cost between 200 and 250 million Euro to construct.

Purpose[edit]

The project is in line with the joint EU strategy for market-based security of supply, which calls for bidirectional interconnection of national grids and specifically for the creation of a Southern Gas Corridor. Whereas the capacity of the gas interconnector project does not fully satisfy the capacity expected in the Southern Gas Corridor, it achieves diversification of sources of supply of natural gas to Bulgaria and helps the countries in the region get greater access to the global natural gas market;[5][6] Azerbaijani natural gas has started to pass through the interconnector.[7]

Project development[edit]

On 14 July 2009, a Memorandum of understanding was signed between Bulgarian Energy Holding EAD, Edison (Italy) and DEPA, which defines the principles for the development and realization of the project. In January 2011, a joint company "ICGB" AD was registered by the same partners that will construct, own and operate the pipeline. The project took off in 2017.[8] Construction works commenced in early 2020 and were completed in the third quarter of 2022.[5] The interconnector is fully operational since October 1.[3][9]

Usage[edit]

In 2023 ICGB held the first annual auction for the interconnector capacity, with 80% of the current 3bcm capacity reserved for the 2024 year.[10]

The ICGB pipe line is connected to the Alexandroupolis INGS which will become operational in March 2024.

In January 2024 Slovakia, Moldova and Ukraine have joined Bulgaria, North Macedonia, Romania, Serbia and Hungary as customers of gas shipped through the ICGB pipeline giving emphasis to the need for expansion of the pipeline from 3 to 5 billion cubic meters of gas.[11]

See also[edit]

References[edit]

  1. ^ Gas Interconnection Greece - Bulgaria (IGB) Archived 2014-02-02 at the Wayback Machine, Ministry of Economy, Energy and Tourism of the Republic of Bulgaria, retrieved 12-11-2012
  • ^ "Greece-Bulgaria gas pipeline to be ready by end of June". www.ekathimerini.com. Kathimerini. Retrieved 30 March 2022.
  • ^ a b "Greece-Bulgaria pipeline starts operations to boost non-Russian gas flows". Reuters. 1 October 2022. Retrieved 1 October 2022.
  • ^ a b "Bulgaria, Greece agree to link pipelines for delivery of Azerbaijan gas". Trend News Agency. 15 July 2009. Retrieved 23 October 2010.
  • ^ a b "New gas pipeline boosts Europe's bid to ease Russian supply". The Independent. 29 April 2022. Retrieved 29 September 2022.
  • ^ "Accelerating energy diversification in Central and Eastern Europe". IEA. 14 September 2022. Retrieved 29 September 2022.
  • ^ "Greece-Bulgaria interconnector: over 303 GWh transported in first days of operations - CEENERGYNEWS". ceenergynews.com. 17 October 2022. Retrieved 23 October 2022.
  • ^ ICGB Brussels 23-24 Octobereuropa.eu Archived 3 May 2022 at the Wayback Machine
  • ^ "Gas interconnector Greece-Bulgaria to start commercial operation on October 1". Balkan Green Energy News. 29 September 2022. Retrieved 29 September 2022.
  • ^ "Bulgaria: Transported volume via IGB gas pipeline exceeded 15.5 million MWh in 2023". 9 January 2024.
  • ^ "Gas to reach Ukraine via Thrace". 20 January 2024.
  • External links[edit]


    Retrieved from "https://en.wikipedia.org/w/index.php?title=Gas_Interconnector_Greece–Bulgaria&oldid=1224950848"

    Categories: 
    Natural gas pipelines in Bulgaria
    Natural gas pipelines in Greece
    BulgariaGreece relations
    Hidden categories: 
    Webarchive template wayback links
    Articles with short description
    Short description is different from Wikidata
    Use dmy dates from October 2022
    Wikipedia articles in need of updating from September 2022
    All Wikipedia articles in need of updating
     



    This page was last edited on 21 May 2024, at 13:38 (UTC).

    Text is available under the Creative Commons Attribution-ShareAlike License 4.0; additional terms may apply. By using this site, you agree to the Terms of Use and Privacy Policy. Wikipedia® is a registered trademark of the Wikimedia Foundation, Inc., a non-profit organization.



    Privacy policy

    About Wikipedia

    Disclaimers

    Contact Wikipedia

    Code of Conduct

    Developers

    Statistics

    Cookie statement

    Mobile view



    Wikimedia Foundation
    Powered by MediaWiki