Jump to content
 







Main menu
   


Navigation  



Main page
Contents
Current events
Random article
About Wikipedia
Contact us
Donate
 




Contribute  



Help
Learn to edit
Community portal
Recent changes
Upload file
 








Search  

































Create account

Log in
 









Create account
 Log in
 




Pages for logged out editors learn more  



Contributions
Talk
 



















Contents

   



(Top)
 


1 Nuclear power  



1.1  Planning  





1.2  Uncertainty  





1.3  Cancellation  







2 Aftermath  





3 References  





4 Footnotes  














Nuclear Energy Board







Add links
 









Article
Talk
 

















Read
Edit
View history
 








Tools
   


Actions  



Read
Edit
View history
 




General  



What links here
Related changes
Upload file
Special pages
Permanent link
Page information
Cite this page
Get shortened URL
Download QR code
Wikidata item
 




Print/export  



Download as PDF
Printable version
 
















Appearance
   

 






From Wikipedia, the free encyclopedia
 


Agency logo

The Nuclear Energy Board (officially titled An Bord Fuinnimh Núicléigh)[1] was an Irish agency charged with developing nuclear power in Ireland. It was established in Ireland on 30 November 1973 by the Nuclear Energy (An Bord Fuinnimh Núicléigh) Act 1971.

The board was responsible in the 1970s for pursuing the policy of developing a nuclear power station, which was to be located at Carnsore Point, County Wexford. This policy ultimately failed and the board gradually faded from public attention, eventually concentrating on nuclear-related environmental reports. It was not a large organisation, with the Electricity Supply Board doing most operational work.

Nuclear power[edit]

Planning[edit]

In 1968, Ireland's economic development required more energy production and the Electricity Supply Board began evaluating ways of diversifying its electricity generation. The Turlough Hill project had just commenced and this was one of the most prestigious engineering projects since the foundation of the state and the Shannon hydroelectric scheme. In the 1970s the need for new energy sources became more urgent, especially after the 1973 energy crisis. In 1975 Bord Gáis was established in order to develop Kinsale gas field, slowing the nuclear energy project as it was hoped it may be an alternative. However, in 1974 planning permission was sought for four reactors with County Wexford County Council, with one to be built immediately, most likely of pressurized water reactor design.

Uncertainty[edit]

The economic slowdown of 1974 and 1975 saw the project temporarily put on hold. When Desmond O'Malley became the new Minister for Industry, Commerce and Energy in 1977 the project once again became a priority of government policy. This time the government wanted to build a 650 MW plant at Carnsore at a cost of £350 million (Punt) at then-prices. In 1979 the project was again postponed, following a change in government when George Colley became the new minister in charge of the project and the incident at Three Mile Island in the United States. Friends of the Earth and other groups lobbied against the plan and in 1981 the Electricity Supply Board and the government announced it was no longer national policy.

Cancellation[edit]

Ultimately the board was remembered for the plans put on and off hold, and resulting immense controversy. Also there was criticism that the government overestimated the need of energy in Ireland in the future; at one point it was estimated that industry would consume 57% of energy by 1990 - internationally this is rather large, as 40% is a typical value. Nevertheless, Ireland in the 1970s was regarded as being in a dangerous position on energy, as 75% of needs were met by oil, and European Economic Community policy was to reduce this below 50% by 1985, after two energy crises.

Aftermath[edit]

After 1981 the Nuclear Energy Board was not immediately abolished, instead rather than becoming nuclear advocate, with the board became redefined in a new role as an environmentalist. The board sponsored a number of reports, in particular on the Sellafield plant which has long been a source of dispute between Ireland and the United Kingdom.

On 1 April 1992 the successor to the board was established, the Radiological Protection Institute of Ireland. The production of electricity for supply to the national grid, by nuclear fission, is currently prohibited under the Electricity Regulation Act 1999 (Section 18).

References[edit]

Nuclear Energy Board Final Report 1973-1992, Dublin 1992. (PDF)

Footnotes[edit]

  1. ^ The official title was An Bord Fuinnimh Núicléigh in the Irish language, however, the English language title — though unofficial — was used in practice.

Retrieved from "https://en.wikipedia.org/w/index.php?title=Nuclear_Energy_Board&oldid=1159272109"

Categories: 
Energy in the Republic of Ireland
Nuclear organizations
Environment of the Republic of Ireland
Science and technology in the Republic of Ireland
Scientific organisations based in the Republic of Ireland
1973 establishments in Ireland
Hidden categories: 
Articles with short description
Short description is different from Wikidata
Articles needing additional references from May 2017
All articles needing additional references
Articles needing additional references from June 2023
Articles lacking in-text citations from June 2023
All articles lacking in-text citations
Articles with multiple maintenance issues
Articles containing Irish-language text
 



This page was last edited on 9 June 2023, at 09:05 (UTC).

Text is available under the Creative Commons Attribution-ShareAlike License 4.0; additional terms may apply. By using this site, you agree to the Terms of Use and Privacy Policy. Wikipedia® is a registered trademark of the Wikimedia Foundation, Inc., a non-profit organization.



Privacy policy

About Wikipedia

Disclaimers

Contact Wikipedia

Code of Conduct

Developers

Statistics

Cookie statement

Mobile view



Wikimedia Foundation
Powered by MediaWiki