Jump to content
 







Main menu
   


Navigation  



Main page
Contents
Current events
Random article
About Wikipedia
Contact us
Donate
 




Contribute  



Help
Learn to edit
Community portal
Recent changes
Upload file
 








Search  

































Create account

Log in
 









Create account
 Log in
 




Pages for logged out editors learn more  



Contributions
Talk
 



















Contents

   



(Top)
 


1 The fields  





2 Development  





3 See also  





4 References  














Saturn Banks Project gas fields







Add links
 









Article
Talk
 

















Read
Edit
View history
 








Tools
   


Actions  



Read
Edit
View history
 




General  



What links here
Related changes
Upload file
Special pages
Permanent link
Page information
Cite this page
Get shortened URL
Download QR code
Wikidata item
 




Print/export  



Download as PDF
Printable version
 
















Appearance
   

 






From Wikipedia, the free encyclopedia
 


The Saturn Banks Project comprises six natural gas reservoirs and gas production facilities in the southern North Sea, 35-55 km north east of Bacton, Norfolk. The fields are under development and first gas is due in 2022.

The fields[edit]

The Saturn Banks Project includes the Blythe, Elgood, Southwark, Elland, Nailsworth and Goddard gas fields in the UK offshore Quadrants 48 and 49.

Details of the gas fields is summarised in the table.[1] [2] [3]

Saturn Banks field data
Field name Blythe Elgood Southwark Elland Nailsworth Goddard
Former name Vulcan South Vulcan East Vulcan North West Glein
Blocks 48/22 48/23 49/21c 49/21a 48/25a,b 48/11
Year discovered 1966 1991 2000 2006 1987 1994
Original licensee Burmah Enterprise Oil ConocoPhillips Silverstone Energy Shell/Exxon Arco
Gas reservoir geology Permian Rotliegend Rotliegend Rotliegend Rotliegend Rotliegend
Gas in place, billion cubic feet 33 22 94.2 55 99.4 132

Development[edit]

The Saturn Banks Project is being developed by IOG plc as the project operator; it holds a 50% stake and CalEnergy Resources (UK) also holds a 50% stake.[1]

The gas fields are developed in stages. The first phase comprised the Blythe, Elgood and Southwark fields. These are developed by offshore platforms, subsea wellheads and pipelines. Details are summarised in the table.[1] [4] [5]

Saturn Banks Installations
Field Blythe Elgood Southwark
Block 4/22 48/23 49/21
Installation name Blythe Southwark
Installation type Fixed steel platform Subsea wellhead Fixed steel platform
Coordinates 53° 18.331'N 01° 23.171'E
Installed June 2021 June 2021
Water depth, metres 30 30 30
Substructure weight, tonnes 1,050 1,300
Topsides weight, tonnes 750 900
No. of legs Monotower 4
No. of Wells 1 1 3
Gas export to Blythe hub on Thames pipeline Blythe Southwark hub on Thames pipeline
Export pipeline length, diameter 24.5 km, 12-inch 9.1 km, 6-inch 5.9 km, 24-inch
Pipeline number (gas) PL4943
Control umbilical/ methanol supply To Elgood From Blythe
Umbilical length, diameter 9.1 km, 5-inch
Umbilical/Pipeline number


The pipelines from Blythe and Southwark platforms are tied into the reused Thames to Bacton 24-inch pipeline (PL370), renamed the Saturn Banks Pipeline System.[4]

In addition to the offshore development the Saturn Banks reception facilities at Bacton gas terminal were installed.[6]

Later phases of the Saturn Banks Project will include the Nailsworth, Elland and Goddard gas fields. Nailsworth is projected to be produced through the Southwark platform.[6]

See also[edit]

References[edit]

  1. ^ a b c "Core Gas Project Phase 1, North Sea". www.nsenergybusiness.com. Retrieved 15 December 2021.
  • ^ "OGA interactive Maps". ogauthority.maps.arcgis.com. Retrieved 15 December 2021.
  • ^ Department of Trade and Industry (1994). The Energy Report. London: HMSO. ISBN 0115153802.
  • ^ a b "IOG renames UK North Sea Project". www.oedigital.com. 26 August 2021. Retrieved 15 December 2021.
  • ^ "IOG North Sea Ltd. and IOG U.K. Ltd. Blythe Hub Development Environmental Statement" (PDF). assets.publishing.service.gov.uk. Retrieved 15 December 2021.
  • ^ a b "IOG plc Operational Update". www.investegate.co.uk. Retrieved 15 December 2021.

  • Retrieved from "https://en.wikipedia.org/w/index.php?title=Saturn_Banks_Project_gas_fields&oldid=1219844590"

    Categories: 
    North Sea energy
    Natural gas fields in the United Kingdom
     



    This page was last edited on 20 April 2024, at 05:26 (UTC).

    Text is available under the Creative Commons Attribution-ShareAlike License 4.0; additional terms may apply. By using this site, you agree to the Terms of Use and Privacy Policy. Wikipedia® is a registered trademark of the Wikimedia Foundation, Inc., a non-profit organization.



    Privacy policy

    About Wikipedia

    Disclaimers

    Contact Wikipedia

    Code of Conduct

    Developers

    Statistics

    Cookie statement

    Mobile view



    Wikimedia Foundation
    Powered by MediaWiki