Jump to content
 







Main menu
   


Navigation  



Main page
Contents
Current events
Random article
About Wikipedia
Contact us
Donate
 




Contribute  



Help
Learn to edit
Community portal
Recent changes
Upload file
 








Search  

































Create account

Log in
 









Create account
 Log in
 




Pages for logged out editors learn more  



Contributions
Talk
 



















Contents

   



(Top)
 


1 Elements of unit commitment problems  



1.1  Management objectives  





1.2  Types of production units  





1.3  Electrical grid models  







2 Uncertainty in unit commitment problems  





3 Integrated Transmission and Distribution Models  





4 See also  





5 References  





6 External links  














Unit commitment problem in electrical power production






Deutsch
 

Edit links
 









Article
Talk
 

















Read
Edit
View history
 








Tools
   


Actions  



Read
Edit
View history
 




General  



What links here
Related changes
Upload file
Special pages
Permanent link
Page information
Cite this page
Get shortened URL
Download QR code
Wikidata item
 




Print/export  



Download as PDF
Printable version
 
















Appearance
   

 






From Wikipedia, the free encyclopedia
 


The unit commitment problem (UC) in electrical power production is a large family of mathematical optimization problems where the production of a set of electrical generators is coordinated in order to achieve some common target, usually either matching the energy demand at minimum cost or maximizing revenue from electricity production. This is necessary because it is difficult to store electrical energy on a scale comparable with normal consumption; hence, each (substantial) variation in the consumption must be matched by a corresponding variation of the production.

Coordinating generation units is a difficult task for a number of reasons:

Because the relevant details of the electrical system vary greatly worldwide, there are many variants of the UC problem, which are often very difficult to solve. This is also because, since some units require quite a long time (many hours) to start up or shut down, the decisions need be taken well in advance (usually, the day before), which implies that these problems have to be solved within tight time limits (several minutes to a few hours). UC is therefore one of the fundamental problems in power system management and simulation. It has been studied for many years,[1][2] and still is one of the most significant energy optimization problems. Recent surveys on the subject[3][4] count many hundreds of scientific articles devoted to the problem. Furthermore, several commercial products comprise specific modules for solving UC, such as MAON[5] and PLEXOS,[6] or are even entirely devoted to its solution.[7]

Elements of unit commitment problems

[edit]

There are many different UC problems, as the electrical system is structured and governed differently across the world. Common elements are:

The decisions that have to be taken usually comprise:

While the above features are usually present, there are many combinations and many different cases. Among these we mention:

Management objectives

[edit]

The objectives of UC depend on the aims of the actor for which it is solved. For a MO, this is basically to minimize energy production costs while satisfying the demand; reliability and emissions are usually treated as constraints. In a free-market regime, the aim is rather to maximize energy production profits, i.e., the difference between revenues (due to selling energy) and costs (due to producing it). If the GenCo is a price maker, i.e., it has sufficient size to influence market prices, it may in principle perform strategic bidding[12] in order to improve its profits. This means bidding its production at high cost so as to raise market prices, losing market share but retaining some because, essentially, there is not enough generation capacity. For some regions this may be due to the fact that there is not enough grid network capacity to import energy from nearby regions with available generation capacity.[13] While the electrical markets are highly regulated in order to, among other things, rule out such behavior, large producers can still benefit from simultaneously optimizing the bids of all their units to take into account their combined effect on market prices.[14] On the contrary, price takers can simply optimize each generator independently, as, not having a significant impact on prices, the corresponding decisions are not correlated.[15]

Types of production units

[edit]

In the context of UC, generating units are usually classified as:

Electrical grid models

[edit]

There are three different ways in which the energy grid is represented within a UC:

When the full AC model is used, UC actually incorporates the optimal power flow problem, which is already a nonconvex nonlinear problem.

Recently, the traditional "passive" view of the energy grid in UC has been challenged. In a fixed electrical network currents cannot be routed, their behavior being entirely dictated by nodal power injection: the only way to modify the network load is therefore to change nodal demand or production, for which there is limited scope. However, a somewhat counter-intuitive consequence of Kirchhoff laws is that interrupting a line (maybe even a congested one) causes a global re-routing of electrical energy and may therefore improve grid performances. This has led to defining the Optimal Transmission Switching problem,[11] whereby some of the lines of the grid can be dynamically opened and closed across the time horizon. Incorporating this feature in the UC problem makes it difficult to solve even with the DC approximation, even more so with the full AC model.[23]

Uncertainty in unit commitment problems

[edit]

A troubling consequence of the fact that UC needs be solved well in advance to the actual operations is that the future state of the system is not known exactly, and therefore needs be estimated. This used to be a relatively minor problem when the uncertainty in the system was only due to variation of users' demand, which on aggregate can be forecasted quite effectively,[24][25] and occurrence of lines or generators faults, which can be dealt with by well established rules (spinning reserve). However, in recent years the production from intermittent renewable production sources has significantly increased. This has, in turn, very significantly increased the impact of uncertainty in the system, so that ignoring it (as traditionally done by taking average point estimates) risks significant cost increases.[22] This had made it necessary to resort to appropriate mathematical modeling techniques to properly take uncertainty into account, such as:

The combination of the (already, many) traditional forms of UC problems with the several (old and) new forms of uncertainty gives rise to the even larger family of Uncertain Unit Commitment[4] (UUC) problems, which are currently at the frontier of applied and methodological research.

Integrated Transmission and Distribution Models

[edit]

One of the major issues with the real-time unit commitment problem is the fact that the electricity demand of the transmission network is usually treated as a "load point" at each distribution system. The reality, however, is that each load point is a complex distribution network with its own sub-loads, generators, and DERs. By simplifying a distribution into load points can lead to extreme operational troubles of the whole power grid. Such problems include high pressure on the power transmission system and reverse power flow from the distribution systems towards the power transmission system. A newly pursued approach for more effectively solving the unit-commitment problem hence is born by Integrated Transmission and Distribution Systems.[26] In such models, the unit commitment problem of the Transmission Systems is usually combined with the Renewable Management Problem of the Distribution Systems by the means of bi-level programming tools.

See also

[edit]

References

[edit]
  1. ^ C.J. Baldwin, K.M. Dale, R.F. Dittrich. A study of the economic shutdown of generating units in daily dispatch. Transactions of the American Institute of Electrical Engineers Power Apparatus and Systems, Part III, 78(4):1272–1282, 1959.
  • ^ J.F. Bard. Short-term scheduling of thermal-electric generators using Lagrangian relaxation. Operations Research 1338 36(5):765–766, 1988.
  • ^ N.P. Padhy. Unit commitment – a bibliographical survey, IEEE Transactions On Power Systems 19(2):1196–1205, 2004.
  • ^ a b M. Tahanan, W. van Ackooij, A. Frangioni, F. Lacalandra. Large-scale Unit Commitment under uncertainty, 4OR 13(2), 115–171, 2015.
  • ^ Maon Model Handbook
  • ^ PLEXOS® Integrated Energy Model
  • ^ Power optimization
  • ^ M. Shahidehpour, H. Yamin, and Z. Li. Market Operations in Electric Power Systems: Forecasting, Scheduling, and Risk Management, Wiley-IEEE Press, 2002.
  • ^ C. Harris. Electricity markets: Pricing, structures and Economics, volume 565 of The Wiley Finance Series. John Wiley and Sons, 2011.
  • ^ A.J. Conejo and F.J. Prieto. Mathematical programming and electricity markets, TOP 9(1):1–53, 2001.
  • ^ a b E.B. Fisher, R.P. O'Neill, M.C. Ferris. Optimal transmission switching, IEEE Transactions on Power Systems 23(3):1346–1355, 2008.
  • ^ A.K. David, F. Wen. Strategic bidding in competitive electricity markets: a literature surveyInProceedings IEEE PES Summer Meeting 4, 2168–2173, 2001.
  • ^ T. Peng and K. Tomsovic. Congestion influence on bidding strategies in an electricity market, IEEE Transactions on Power Systems 18(3):1054–1061, August 2003.
  • ^ A.J. Conejo, J. Contreras, J.M. Arroyo, S. de la Torre. Optimal response of an oligopolistic generating company to a competitive pool-based electric power market, IEEE Transactions on Power Systems 17(2):424–430, 2002.
  • ^ J.M. Arroyo, A.J. Conejo. Optimal response of a thermal unit to an electricity spot market, IEEE Transactions on Power Systems 15(3):1098–1104, 2000.
  • ^ J. Batut and A. Renaud. Daily scheduling with transmission constraints: A new class of algorithms, IEEE Transactions on Power Systems 7(3):982–989, 1992.
  • ^ G. Morales-España, J.M. Latorre, A. Ramos. Tight and Compact MILP Formulation of Start-Up and Shut-Down Ramping in Unit Commitment, IEEE Transactions on Power Systems 28(2), 1288–1296, 2013.
  • ^ A. Frangioni, C. Gentile. Solving Nonlinear Single-Unit Commitment Problems with Ramping Constraints, Operations Research 54(4), 767–775, 2006.
  • ^ E.C. Finardi and E.L. Da Silva. Solving the hydro unit commitment problem via dual decomposition and sequential quadratic programming, IEEE Transactions on Power Systems 21(2):835–844, 2006.
  • ^ F.Y.K. Takigawa, E.L. da Silva, E.C. Finardi, and R.N. Rodrigues. Solving the hydrothermal scheduling problem considering network constraints., Electric Power Systems Research 88:89–97, 2012.
  • ^ A. Borghetti, C. D’Ambrosio, A. Lodi, S. Martello. A MILP approach for short-term hydro scheduling and unit commitment with head-dependent reservoir, IEEE Transactions on Power Systems 23(3):1115–1124, 2008.
  • ^ a b A. Keyhani, M.N. Marwali, and M. Dai. Integration of Green and Renewable Energy in Electric Power Systems, Wiley, 2010.
  • ^ K.W. Hedman, M.C. Ferris, R.P. O’Neill, E.B. Fisher, S.S. Oren. Co-optimization of generation unit commitment and transmission switching with n − 1 reliability, IEEE Transactions on Power Systems 25(2):1052–1063, 2010.
  • ^ E.A. Feinberg, D. Genethliou. Load Forecasting, in Applied Mathematics for Restructured Electric Power Systems, J.H. Chow, F.F. Wu, and J. Momoh eds., Springer, 269–285, 2005
  • ^ H. Hahn, S. Meyer-Nieberg, S. Pickl. Electric load forecasting methods: Tools for decision making, European Journal of Operational Research 199(3), 902–907, 2009
  • ^ Fathabad, Abolhassan Mohammadi; Cheng, Jianqiang; Pan, Kai (2021-01-01), Ren, Jingzheng (ed.), "Chapter 5 - Integrated power transmission and distribution systems", Renewable-Energy-Driven Future, Academic Press, pp. 169–199, ISBN 978-0-12-820539-6, retrieved 2021-01-09
  • [edit]
    Retrieved from "https://en.wikipedia.org/w/index.php?title=Unit_commitment_problem_in_electrical_power_production&oldid=1130016692"

    Category: 
    Mathematical optimization in business
     



    This page was last edited on 28 December 2022, at 06:31 (UTC).

    Text is available under the Creative Commons Attribution-ShareAlike License 4.0; additional terms may apply. By using this site, you agree to the Terms of Use and Privacy Policy. Wikipedia® is a registered trademark of the Wikimedia Foundation, Inc., a non-profit organization.