1 Valley Line Southeast (Downtown to Mill Woods)  





2 Valley Line West (Downtown to Lewis Farms)  





3 Service levels  





4 Stations  



4.1  Valley Line Southeast  





4.2  Valley Line West (under construction)  







5 Notes  





6 References  





7 External links  














Valley Line (Edmonton)







 

Edit links
 









Article
Talk
 

















Read
Edit
View history
 








Tools
   


Actions  



Read
Edit
View history
 




General  



What links here
Related changes
Upload file
Special pages
Permanent link
Page information
Cite this page
Get shortened URL
Download QR code
Wikidata item
 




Print/export  



Download as PDF
Printable version
 




In other projects  



Wikimedia Commons
 
















Appearance
   

 





Route map: 


From Wikipedia, the free encyclopedia
 


Valley Line
A Valley Line train heading east on 102 Avenue in Downtown Edmonton
Overview
LocaleEdmonton
Termini
  • Mill Woods
  • Stations
    • 12 (Phase 1)
    • 16 (Phase 2)[1]
    • 28 (Total)
    Service
    TypeLight rail
    SystemEdmonton LRT
    Operator(s)Edmonton Transit Service
    Depot(s)Gerry Wright Operations and Maintenance Facility[2]
    History
    Planned opening
    • Phase 2: 2028[3]
    Opened
    • Phase 1: November 4, 2023
    Technical
    Line length13.1 km (8.1 mi)
    (27 km at full build-out)
    Number of tracks2
    CharacterAt-grade, elevated, street running
    Track gauge1,435 mm (4 ft 8+12 in) standard gauge
    Electrification750 V DC Overhead line
    Operating speed80 km/h (50 mph) maximum[4]

    Route map

    Map Valley Line highlighted in green


    0Phase 2 (2028)

    Lewis Farms

    Aldergrove/Belmead
    (182 Street)

    West Edmonton Mall

    Misericordia

    Meadowlark

    Glenwood/Sherwood
    (95 Avenue)

    Jasper Place (156 Street)

    Stony Plain Rd/149 Street

    Grovenor/142 Street

    Glenora

    Groat Road

    124 Street

    Brewery/120 Street

    The Yards/116 Street

    MacEwan Arts/112 Street

    NorQuest (107 Street)

    Alex Decoteau
    (106/105 Street)

    102 Street

    Churchill
    Capital Line Metro Line

    Capital and
    Metro lines

    Quarters

    Tawatinâ Bridge over
    North Saskatchewan River

    Muttart

    Strathearn

    Holyrood

    Bonnie Doon

    Avonmore

    Davies
    Parking Davies Transit Centre

    Gerry Wright OMF

    Millbourne/Woodvale

    Grey Nuns

    Mill Woods
    Mill Woods Transit Centre

    Handicapped/disabled access All stations are accessible
  • talk
  • edit
  • The Valley Line is a low-floor urban light rail line in Edmonton, Canada. The 13.1-kilometre (8.1 mi) line runs southeast from downtownat102 Street stoptoMill Woods Town CentreatMill Woods stop and connects to the Capital and Metro lines at Churchill station, downtown. The line is being constructed in phases, with phase 1 being the current open 12-station portion between 102 Street and Mill Woods that commenced operations on November 4, 2023. The second phase, consisting of the 14-kilometre (8.7 mi), 16-station portion between 102 Street and Lewis Farms, began construction in 2021 and is expected to be completed in 2028.[5][6][3][7] Upon completion, the entire Valley Line is expected to serve more than 100,000 commuters daily,[8] nearly matching the current Capital Line and Metro Line in terms of capacity and ridership.

    Unlike the other trains in the system, the Valley Line operates low-floor Bombardier Flexity Freedom trains, which were first designed for Line 5 Eglinton in Toronto.[9] Forty other new low-floor light rail vehicles were ordered in 2021 from Hyundai Rotem for the Valley Line, to be put in service when phase 2 to Lewis Farms opens.[10]

    Valley Line Southeast (Downtown to Mill Woods)[edit]

    Inside a Valley Line light rail vehicle (LRV) as it travels toward Mill Woods, 2023

    Planning studies for an LRT route from downtown to Mill Woods began in early 2009.[11] In December 2009, Edmonton City Council approved a new low-floor train route that would leave a new ground-level station at Churchill Square on 102 Avenue between 100 and 99 Streets before stopping in The Quarters redevelopment on 102 Avenue between 97 Street and 96 Street. From here the route enters a tunnel and travels beneath 95 Street descending into the river valley to cross the North Saskatchewan River on the new Tawatinâ Bridge,[12] east of Louise McKinney Park. The route then climbs the hill adjacent to Connors Road then proceeds east along 95 Avenue and southbound at 85 Street. The route travels southbound along 85 Street, crossing the intersection north of Bonnie Doon Mall and shifting to 83 Street, continuing south and east. Just north of Argyll Road, the line is lifted onto an elevated guideway over Davies Industrial. Finally, the line proceeds south along 75/66 Street until it reaches Mill Woods Town Centre. Within this line the proposed stops are: Quarters, Muttart, Strathearn, Holyrood, Bonnie Doon, Avonmore, Davies (to include a bus terminal and park & ride),[13] Millbourne/Woodvale, Grey Nuns, and Mill Woods Town Centre. The maintenance and storage of vehicles for the line is at the Gerry Wright Operations and Maintenance Facility (opened in 2018), at Whitemud Drive and 75 Street.[14]

    On June 1, 2011, City Council approved $39 million in funding to proceed with preliminary engineering for the Valley Line.[11] In November 2011 City Council voted to allocate $800 million to the project, with the hopes of starting construction by 2014 and an expected completion date of 2018.[15] A funding plan was approved in October 2012 in which the city would contribute $800 million into the project with the remaining $1 billion coming from the provincial and federal governments.[16]

    On February 15, 2012, city council approved the Downtown LRT concept plan. The Downtown LRT Project became part of the Southeast to West LRT project.[17] The city hoped to have money in place by the end of 2013 for the $1.8-billion LRT line from downtown to Mill Woods to start construction in 2016. City council committed $800 million, the federal government invested $250 million, and $235 million would come from the provincial government, leaving a $515 million funding gap delaying the project.[18] On March 11, 2014, it was announced that the project would be completely funded[19][20] with an additional $150 million from the federal government and $365 million from the provincial government.[21][22]

    Land procurement began in 2011[23] and utility relocation began in 2013,[24][25][26][27] completion of the first stage was expected in 2020.[28][29] The official groundbreaking of the Valley Line was on April 22, 2016.[30][31]

    Valley Line and the Davies Transit Centre under construction (January 2021)

    In September 2019, it was revealed that the segment of the line was a year behind schedule of its projected December 2020 opening date. The 2019 construction season posed a challenge to crews due to frequent rain.[32]

    In December 2019, completion of the line was pushed back until 2021 after TransEd found a car-sized piece of concrete underneath the north berm of the Tawatinâ Bridge.[33] The line's completion was subsequently delayed to late 2021,[34] then to first quarter of 2022, and again to July 2022.[35][36]

    The Churchill connector, which connects the Valley Line and above-ground lines to the Churchill LRT station, under construction

    On August 10, 2022, the City of Edmonton and TransEd announced another delay, as inspections in mid-July found cracks in three supporting piers on elevated portions of the line.[37] Further inspections revealed that 30 of the 45 piers were cracked. An initial assessment named lateral thermal expansion as a potential factor in creating the cracks. Later analysis determined that the rebar was inadequate, and ideas were being tested as to how to best repair the piers.[38][39] Before the damaged piers were discovered, trains were being tested on tracks between the Gerry Wright OMF and the Mill Woods stop.[40] During pier remediation, testing took place only on portions of the line that were not elevated.[41] On January 3, 2023, the structural repairs of the cracked pillars were complete, and testing expanded to all sections of the line, including the elevated portions.[42]

    On June 26, 2023, TransEd announced they were replacing 140 kilometres (87 mi) of signalling cables in ducts, as some were oxidized. The work started immediately, and was expected to be done from downtown to Whitemud Drive by the end of August. The remaining section south to Mill Woods was slated to be done after the line opened, with the work undertaken at night when no trains are running. On October 24, the City of Edmonton announced that the line would open on November 4 after testing resumed and independent certifiers submitted final approval.[43] The inaugural train had later departed from Mill Woods stop at 5:15 am that morning.[44]

    Valley Line West (Downtown to Lewis Farms)[edit]

    An expansion to Lewis Farms, with the West Edmonton Mall en route, is in the early stages of construction as part of the 27-kilometre (17 mi) Valley Line.

    The option approved by Council in 2010 has the west LRT extension run from downtown along 104 Avenue and Stony Plain Road to 156 Street, then south on 156 Street to Meadowlark Health & Shopping Centre, and then west along 87 Avenue to West Edmonton Mall and beyond. Proponents of this route cited opportunities for transit-oriented development.[45][46]

    In 2016, the Valley Line West received funding through the Government of Canada’s Public Transit Infrastructure Fund (PTIF) to review the preliminary design that was completed in 2013. The funding covers work to determine the most appropriate project delivery method (P3, for example) and to develop a business case for construction funding.

    Preparation work, such as the relocation of underground utilities and clearing of land along the route, began in 2019.[47]

    The Government of Canada provided approximately $948 million for the Valley Line West expansion, and the Government of Alberta in 2020 committed approximately $1.04 billion for the project.[48] As of 2020 the expansion was projected to cost approximately $2.67 billion in total.[49] In 2020, the City of Edmonton selected Marigold Infrastructure Partners to build the western section of the Valley Line.[50] Early construction work began in 2021 and the line formally commenced construction on May 27, 2022. It is expected to be completed in 2028.[3]

    Service levels[edit]

    Trains run every 10 minutes, but run every 5 minutes at peak times. Service starts daily at 5:15 am from the 102 Street stop. From the Mill Woods stop, service starts at 5:00 am on weekdays, and 5:15 am on weekends. Last trains depart both stops at 1:00 am Monday–Saturday, and 12:30 am on Sundays.[51]

    Stations[edit]

    Valley Line Southeast[edit]

    Stop Grade-level Transfer Area Opened Location[52]
    102 Street stop Surface Downtown November 4, 2023 53°32′35N 113°29′41W / 53.54306°N 113.49472°W / 53.54306; -113.49472 (102 Street stop)
    Churchill station Surface[a] Capital Line Capital Line
    Metro Line Metro Line
    Downtown November 4, 2023 53°32′36N 113°29′23W / 53.54333°N 113.48972°W / 53.54333; -113.48972 (Churchill station)
    Quarters stop Surface Downtown November 4, 2023 53°32′40N 113°29′1W / 53.54444°N 113.48361°W / 53.54444; -113.48361 (Quarters stop)
    Muttart stop Surface Southeast November 4, 2023 53°32′11N 113°28′46W / 53.53639°N 113.47944°W / 53.53639; -113.47944 (Muttart stop)
    Strathearn stop Surface Southeast November 4, 2023 53°31′54N 113°27′46W / 53.53167°N 113.46278°W / 53.53167; -113.46278 (Strathearn stop)
    Holyrood stop Surface Southeast November 4, 2023 53°31′40N 113°27′27W / 53.52778°N 113.45750°W / 53.52778; -113.45750 (Holyrood stop)
    Bonnie Doon stop Surface Southeast November 4, 2023 53°31′10N 113°27′20W / 53.51944°N 113.45556°W / 53.51944; -113.45556 (Bonnie Doon stop)
    Avonmore stop Surface Southeast November 4, 2023 53°30′34N 113°27′18W / 53.50944°N 113.45500°W / 53.50944; -113.45500 (Avonmore stop)
    Davies station Elevated Southeast November 4, 2023 53°30′0″N 113°26′39W / 53.50000°N 113.44417°W / 53.50000; -113.44417 (Davies station)
    Millbourne/Woodvale stop Surface Southeast November 4, 2023 53°28′30N 113°26′20W / 53.47500°N 113.43889°W / 53.47500; -113.43889 (Millbourne stop)
    Grey Nuns stop Surface Southeast November 4, 2023 53°27′46N 113°26′4W / 53.46278°N 113.43444°W / 53.46278; -113.43444 (Grey Nuns stop)
    Mill Woods stop Surface Southeast November 4, 2023 53°27′30N 113°25′50W / 53.45833°N 113.43056°W / 53.45833; -113.43056 (Mill Woods stop)

    Valley Line West (under construction)[edit]

    Notes[edit]

    1. ^ The Valley Line platform at Churchill is at street level; connections to the Capital Line and Metro Line are made inside the underground station.

    References[edit]

    1. ^ "Valley Line – West". Edmonton.ca. Retrieved February 2, 2019.
  • ^ "Gerry Wright Biography" (PDF). City of Edmonton. Archived (PDF) from the original on September 28, 2015. Retrieved October 25, 2023.
  • ^ a b c "Valley Line West LRT". majorprojects.alberta.ca. Government of Alberta. Retrieved September 17, 2021.
  • ^ "FLEXITY Freedom" (PDF). Bombardier Transportation. Archived from the original (PDF) on September 6, 2014. Retrieved May 1, 2013.
  • ^ "Valley Line (SE to West LRT): Mill Woods to Lewis Farms". Edmonton Transit System. 2015. Archived from the original on February 9, 2016. Retrieved June 16, 2015.
  • ^ "Valley Line LRT Animation". City of Edmonton. December 3, 2013. Retrieved June 16, 2015.
  • ^ "Edmonton Valley Line West LRT celebrates first construction season". Mass Transit. May 22, 2022. Retrieved October 25, 2023.
  • ^ "EllisDon -Edmonton Valley Line LRT".
  • ^ "Bombardier Wins Order to Supply Light Rail Transit System for City of Edmonton's Valley Line in Canada". Bombardier Transportation. Retrieved February 12, 2016.
  • ^ Cook, Dustin (November 10, 2021). "City of Edmonton selects Hyundai Rotem Company to provide 40 light-rail vehicles for Valley Line West LRT". Edmonton Journal. Retrieved November 10, 2021.
  • ^ a b "Southeast LRT Project History". City of Edmonton. Retrieved May 26, 2012.
  • ^ "Southeast LRT (Valley Line) Names Approved". City of Edmonton Naming Committee. Archived from the original on November 14, 2013. Retrieved November 14, 2013.
  • ^ "Southeast to West LRT – Approved Concept Plan Amendment" (PDF). City of Edmonton. Retrieved November 19, 2012.
  • ^ "Operations and Maintenance Facility" (PDF). City of Edmonton. Archived from the original (PDF) on March 26, 2014. Retrieved August 28, 2014.
  • ^ "City fast-tracks LRT expansion with push for $800 million". Edmonton Journal. Postmedia Network. Retrieved November 19, 2012.
  • ^ Kent, Gordon (October 17, 2012). "Council approves P3 funding plan for southeast LRT line". Edmonton Journal. Postmedia Network. Archived from the original on February 3, 2013. Retrieved November 19, 2012.
  • ^ "Southeast to West LRT: Mill Woods to Lewis Farms". City of Edmonton. Archived from the original on February 9, 2016. Retrieved May 27, 2012.
  • ^ Dykstra, Matt (November 13, 2013). "Federal government projects a $3.7 billion budget surplus which could help Edmonton LRT line". Edmonton Sun. Retrieved November 14, 2013.
  • ^ Tumilty, Ryan (March 11, 2014). "Southeast LRT funding includes $200 million interest-free provincial loan". Metro News. Retrieved March 12, 2014.
  • ^ Kent, Gordon (March 11, 2014). "Southeast LRT on track after province promises to fill $600 million funding gap (with video)". Edmonton Journal. Archived from the original on April 18, 2014. Retrieved March 12, 2014.
  • ^ Simons, Paula (May 26, 2014). "Cash for Valley Line is fine, but transit funding must be consistent". Edmonton Journal. Archived from the original on June 20, 2014. Retrieved May 27, 2014.
  • ^ Dykstra, Matthew (May 26, 2014). "Edmonton gets a final piece of funding for southeast portio of Valley LRT line". Edmonton Sun. Retrieved May 27, 2014.
  • ^ "SIRE Public Access". sirepub.edmonton.ca. Retrieved June 2, 2016.
  • ^ Edmonton, City of (June 2, 2016). "Project History :: City of Edmonton". www.edmonton.ca. Retrieved June 2, 2016.
  • ^ "Fact Sheet; Valley Line (SE to WEST LRT); May 2014" (PDF). City of Edmonton. May 30, 2014. Retrieved August 28, 2014.
  • ^ "Connors Road Construction". EPCOR. Retrieved July 24, 2014.
  • ^ "2014 Construction on your streets". City of Edmonton. Retrieved July 25, 2014.
  • ^ "City of Edmonton Valley Line Stage 1 – Light Rail Transit (LRT) Project Environmental Impact Screening Assessment Update" (PDF). Edmonton. City of Edmonton. Retrieved May 1, 2016.
  • ^ "Valley Line (SE to West LRT)" (PDF). City of Edmonton. September 2013. Retrieved August 28, 2014.
  • ^ Bartko, Karen (April 12, 2016). "Valley Line LRT construction to start April 22, says new website". Corus Entertainment Inc. Global News Edmonton. Retrieved May 1, 2016.
  • ^ "Valley Line (SE to West LRT): Mill Woods to Lewis Farms". Edmonton. City of Edmonton. Archived from the original on February 9, 2016. Retrieved May 1, 2016.
  • ^ Dyer, Kelsey (September 6, 2019). "'Get it finished': Valley Line LRT project facing delays". Edmonton. Retrieved September 8, 2019.
  • ^ Labine, Jeff (December 11, 2019). "Concrete mass in river delaying Valley Line southeast LRT | Edmonton Journal". Retrieved December 13, 2019.
  • ^ Rosove, Jay (June 14, 2021). "Edmonton's newest LRT Line expected to be running by late 2021". CTV News Edmonton. Retrieved September 17, 2021.
  • ^ "Opening of Valley Line Southeast LRT delayed again as first train crosses Tawatinâ Bridge".
  • ^ "DBRS Morningstar Comments on TransEd Partners General Partnership's Delay in Service Commencement". www.dbrsmorningstar.com. December 22, 2021. Retrieved December 28, 2021.
  • ^ Riebe, Natasha (August 10, 2022). "Edmonton's Valley Line Southeast LRT delayed again after inspectors discover cracks in piers". CBC News. Retrieved August 12, 2022.
  • ^ Gibson, Caley (September 2, 2022). "More cracks discovered in concrete piers along Valley Line LRT southeast extension – Edmonton". Global News. Retrieved September 3, 2022.
  • ^ Wakefield, Jonny (November 19, 2022). "'Profoundly disappointed': Two-thirds of concrete pillars on new Edmonton LRT line now need repairs". Edmonton Journal. Retrieved November 20, 2022.
  • ^ "Light Rail Vehicle (LRV) Train System Testing on 66 Street – TransEd Valley Line LRT". Retrieved February 23, 2021.
  • ^ Smith, Madeline (August 10, 2022). "Long-delayed $1.8-billion Valley Line LRT stymied yet again". Edmonton Journal. Retrieved August 12, 2022.
  • ^ Valley Line Southeast LRT [@yegvalleyLRT] (January 3, 2023). "Now that the structural repairs are completed, trains are moving along the elevated sections of the track" (Tweet) – via Twitter.
  • ^ Antoneshyn, Alex (October 24, 2023). "Valley Line Southeast LRT to open to public in November". CTV News Edmonton. Retrieved October 24, 2023.
  • ^ Hunt, Stephen (November 4, 2023). "'The most Edmonton experience I've ever had': Hundreds of transit lovers show up to ride first Valley Line train". CTV News Edmonton. Bell Media. Retrieved November 4, 2023.
  • ^ Kent, Gordon (September 3, 2009). "Edmonton unveils west and south LRT plans". Archived from the original on November 7, 2009. Retrieved December 2, 2011.
  • ^ "City Proposes Southeast and West LRT Routes". September 3, 2009. Archived from the original on June 16, 2011. Retrieved December 2, 2011.
  • ^ "Keeping track: Progress on Valley Line West LRT". Transforming Edmonton. City of Edmonton. January 9, 2020. Archived from the original on May 11, 2022. Retrieved March 15, 2024.
  • ^ Edmonton, City of (September 30, 2020). "Valley Line". www.edmonton.ca. Retrieved September 30, 2020.
  • ^ "Valley Line West LRT expansion lives on after call from councillor to rescind approved funding". Edmonton Journal. Retrieved September 30, 2020.
  • ^ Gibson, Carly (October 21, 2020). "City of Edmonton selects Marigold Infrastructure Partners for Valley Line West LRT project". Global News. Retrieved October 25, 2023.
  • ^ "Edmonton's Valley Line Southeast LRT set to open Nov. 4". CBC. October 24, 2023. Retrieved October 25, 2023.
  • ^ a b "Valley Line LRT Maps". City of Edmonton. Retrieved July 9, 2017.
  • External links[edit]

    KML is not from Wikidata

    Retrieved from "https://en.wikipedia.org/w/index.php?title=Valley_Line_(Edmonton)&oldid=1231429209"

    Categories: 
    Edmonton LRT
    Rapid transit lines in Canada
    Valley Line (Edmonton)
    Railway lines opened in 2023
    2023 establishments in Alberta
    Hidden categories: 
    Articles with short description
    Short description is different from Wikidata
    Use Canadian English from May 2024
    All Wikipedia articles written in Canadian English
    Use mdy dates from May 2024
    Articles containing potentially dated statements from 2020
    All articles containing potentially dated statements
    Pages using gadget WikiMiniAtlas
    Lists of coordinates
    Geographic coordinate lists
    Articles with Geo
    Commons category link is on Wikidata
    Articles using KML not from Wikidata
    Pages using the Kartographer extension
     



    This page was last edited on 28 June 2024, at 06:56 (UTC).

    Text is available under the Creative Commons Attribution-ShareAlike License 4.0; additional terms may apply. By using this site, you agree to the Terms of Use and Privacy Policy. Wikipedia® is a registered trademark of the Wikimedia Foundation, Inc., a non-profit organization.



    Privacy policy

    About Wikipedia

    Disclaimers

    Contact Wikipedia

    Code of Conduct

    Developers

    Statistics

    Cookie statement

    Mobile view



    Wikimedia Foundation
    Powered by MediaWiki