MumbaiNagpur Expressway





Article  

Talk  



Language  

Watch  

Edit  





The Samruddhi MahamargorNagpur-Mumbai Expressway (officially known as Hindu Hrudaysamrat Balasaheb Thackeray Maharashtra Samruddhi Mahamarg) and Maharashtra Expressway-2 (ME-2), is a partially opened 6-lane wide (expandable to 8), 701-km long access-controlled expresswayinMaharashtra, India. It is amongst the country's longest greenfield road projects,[4] which will connect the two capital cities of the state, its capital, Mumbai, and its third-largest and alternate capital city, Nagpur.[5] The project is being led by the state infrastructure arm Maharashtra State Road Development Corporation (MSRDC),[6] and is designed under the Engineering, Procurement and Construction (EPC) model.[7]

Mumbai–Nagpur Expressway
Hindu Hrudaysamrat Balasaheb Thackeray Maharashtra Samruddhi Mahamarg

Map

Mumbai-Nagpur Expressway in red
Samruddhi Expressway 2.jpg
Section of the expressway in Nashik district
Route information
Maintained by Maharashtra State Road Development Corporation (MSRDC)
Length701 km (436 mi)
StatusPartially opened
Existed11 December 2022
(Phase 1 - Nagpur to Shirdi)
26 May 2023
(Phase 2 - Shirdi to Bharvir Khurd)[1]
4 March 2024
(Phase 3 - Bharvir KhurdtoIgatpuri)[2]
August 2024
(Phase 4 - Igatpuri to Mumbai MMR)[3]–present
Major junctions
West endAmane village, Thane district
East endShivmadka village, Nagpur district
Location
CountryIndia
StateMaharashtra
DistrictsNagpur, Wardha, Amravati, Washim, Buldhana, Jalna, Chatrapati Sambhaji Nagar, Ahmednagar, Nashik, Thane
Major citiesBhiwandi, Kalyan, Nashik, Shirdi, Chatrapati Sambhaji Nagar, Jalna, Wardha and Nagpur
Highway system
State Highways in Maharashtra

With the route alignment connecting Shivmadka village in Nagpur districttoAmane villageinThane district, the expressway is capable of providing an enhanced connectivity to the Marathwada and Vidarbha regions. The total project cost, including the land acquisition cost, is around 55,000 crore (equivalent to 580 billion or US$7.0 billion in 2023).[8][9] The Government of Maharashtra believes that the expressway will become a prosperity corridor for the overall socio-economic growth of the state.

Route alignment

edit

The Mumbai–Nagpur Expressway will travel through 10 key districts directly and 14 districts indirectly[10] via feeder roads, 24 talukas, and 392 villages. The 10 main districts are Nagpur, Wardha, Amravati, Washim, Buldhana, Jalna, Aurangabad, Nashik, Ahmednagar and Thane. The other 14 districts include Chandrapur, Bhandara, Gondia, Gadchiroli, Yavatmal, Akola, Hingoli, Parbhani, Nanded, Beed, Dhule, Jalgaon, Palghar and Raigad. Yavatmal City is going to Connect with Four Lane road to Samruddhi Expressway and Amravati too.Four Lane Road will be construct between Yavatmal City to Badnera. [11]

Cities and towns

edit

Below are the lists of cities/towns through which the Mumbai–Nagpur Expressway will connect:

Enhanced connectivity

edit

To create a fast logistics gateway for national and international trade, the expressway will connect the country's largest container port JNPT[12]inMumbai to Mihan in Nagpur. The expressway will allow access to several industrial and economic corridors through 24 interchanges[13] at strategic locations. It will widely connect the Delhi–Mumbai Industrial Corridor, BengaluruChennai Economic Corridor, Western Dedicated Freight Corridor, Eastern Dedicated Freight Corridor, Chennai–Vizag Economic Corridor and Golden Quadrilateral. Apart from JNPT other seaports including Kandla MBPT, Mormugao, New Mangalore, Kochi, Chennai, Visakhapatnam and Ennore will also have indirect connectivity.

Characteristics and design

edit

Characteristics

edit

Design

edit

Entry/Exit list

edit
District Location Chainage (km) Name/Code Notes
Nagpur Shivmadka/ Nagpur end 0+000 IC/01 (Expressway starts here)
Nagpur MIDC Buti Bori 6+700 IC/02
Wardha Seldoh Wadgaon Bakshi Dry Port IC/03
Wardha Yelkeli/ Wardha City IC/04
Wardha Virul/(Arvi-Pulgaon) IC/05
Amravati Dhamangaon IC/06
Amravati Shivni/ Yavatmal- Amaravati IC/07
Washim Karanja Lad IC/08
Washim Shelu Bazaar Wanoza IC/09
Washim Malegaon IC/10
Buldhana Mehkar IC/11
Buldhana Dusarbid IC/12
Buldhana Sindhkhed Raja IC/13
Jalna Nidhona/ Jalna City IC/14
Aurangabad Shendra MIDC IC/15
Aurangabad Aurangabad City IC/16
Aurangabad Maliwada/ Verul IC/17
Aurangabad Hadas Pimpalgaon/ Lasur IC/18
Aurangabad Vaijapur IC/19
Aurangabad Shirdi IC/20

Construction

edit

To expedite the pre-construction work on the expressway, MSRDC decided to divide the design work into 5 packages and hired a separate consultancy firm to prepare the Detailed Project Report (DPR) for each package. On 31 May 2017, the Government of Maharashtra incorporated 'Nagpur Mumbai Super Communication Expressway Limited', a special purpose vehicle (SPV) to manage the financial requirement for the construction and operation of this project.

The construction work of 701 km long Mumbai–Nagpur Expressway is divided into 16 packages, with work awarded to 13 different contractors including Afcons Infrastructure, Larsen & Toubro (L&T) and Reliance Infrastructure.

Sr. No. Package Length in km Contractor
1. Shivmadka (Nagpur)–Khadki/Amgaon (Wardha) 31.0 Megha Engineering[30]
2. Khadki/Amgaon (Wardha)–Pimpalgaon (Wardha) 58.4 Afcons Infrastructure[31]
3. Ashta (Amravati)–Wadhona Ramnath (Amravati) 73.3 NCC Limited
4. Donad Bk (Washim)–Januna Bk (Washim) 54.3 PNC Infratech[32]
5. Kinhiraja (Washim)–Kenwad (Washim) 42.8 Apco Infratech
6. Belgaon (Buldhana)–Parda (Buldhana) 36.1 Apco Infratech
7. Banda (Buldhana)–Sawargaon Mal (Buldhana) 51.2 Reliance Infrastructure[33]
8. Navha (Jalna)– xx (Jalna) 42.7 Montecarlo Construction[34]
9. Bendewadi (Aurangabad)–Fatiyabad (Aurangabad) 54.4 Megha Engineering
10. Fatiyabad (Aurangabad)–Surala (Aurangabad) 57.9 Larsen & Toubro (L&T)[35]
11. Dhotre (Ahmednagar)–Derde Korhale (Ahmednagar) 29.3 Gayatri Projects[36]
12. Pathare (Nashik)–Sonari (Nashik) 45.6 Dilip Buildcon Limited[37]
13. Sonari (Nashik)–Taranganpada (Nashik) 45.6 BSCPL–GVPR JV (joint venture)
14. Pimpri Sadroddin (Nashik)–Vashala Bk (Thane) 13.1 Afcons Infrastructure
15. Vashala Bk (Thane)–Birwadi (Thane) 28.0 Navayuga Engineering Co. (NEC)
16. Birwadi (Thane)–Amane (Thane) 37.0 Navayuga Engineering Co. (NEC)

As of 31 May 2021, out of the total 1699 structures including flyovers, viaducts, major and minor bridges, tunnels, interchanges, etc., construction of 1286 structures has already been completed and the construction of 253 structures are inching towards completion. Total 6 tunnels will be built along the expressway and the construction for all of the tunnels is underway in full swing.

New township development

edit

The Government of Maharashtra has authorized MSRDC to act as the New Town Development Authority to venture into the long-term development of 19 new towns [38] at strategic nodes, which is also coined as 'Krushi Samruddhi Nagar.' The provisions are enacted under sub-sec (1) and section 113 of the MR & TP Act, 1966. The developmental objective to propose these new towns is to encourage the self-employment potential of the regional population through their primitive occupation i.e., agriculture or agro-related businesses.

Every township developed under the initiative of Krushi Samruddhi Nagar will be built in a land area of approximately 1000-1500 hectares. The new towns shall serve as the utility economic nodes for food processing industry, integrated logistics,[39] and domestic food markets along with education centers, skill development institutes, healthcare facilities, and commercial and residential housings. The new townships will offer huge industrial land-banks with a focus on dedicated export-oriented infrastructure and integrated logistics to ease supply chain with enhanced road connectivity for domestic markets.

The 19 new towns[40] will be developed at strategic intersections at a distance of 30 to 40 km[41] from each other. These towns will be developed in two phases; phase one includes seven townships while the remaining eleven townships will be developed in phase two. The new towns will encompass essential facilities including schools, Industrial Training Institutes (ITIs), skill development centers, institutes providing technical education and amp, higher education, hospitals, police stations, playgrounds, open spaces, parks and sports complexes. The new townships will be easily accessible from main roads, feeder roads, national or state highways intersecting the Samruddhi Expressway through the public transport system. The MSRDC adopted land pooling model[42] for land acquisition,[43] wherein 30 percent of the total land acquired under 'Krushi Samruddhi Kendra' program will be returned to landowners. The farmers will also receive compensation of Rs 50,000 per hectare for non-irrigated land and Rs 1 lakh every year for irrigated land for the next 10 years. Based on the suggestions from Wildlife Institute of India (WII), wildlife mitigation measures[44][45] are planned and necessary structures like cattle underpasses[46] are being built for uninterrupted wildlife movement. Around 320 private communicators[47] were trained and deployed by MSRDC for land acquisition negotiations with prospecting landowners.

Inter-connectivity

edit

Following will either connect or act as an alternative to the Mumbai–Nagpur Expressway:

Status updates

edit

Accidents

edit

01/08/2023 - 17 people were dead and 3 were injured when under-construction crane had collapsed on workers in Thane in early hours of Tuesday morning. PM Modi had announced 2 lakh exgretia for died.[75]

See also

edit

References

edit
  1. ^ "Eknath Shinde, Devendra Fadnavis to open Phase-II Samruddhi Mahamarg on May 26". The Deccan Herald. 25 May 2023.
  • ^ "25-km more of Samruddhi Mahamarg to be opened on March 4 in Maharashtra". The Indian Express. 29 February 2024.
  • ^ "Samruddhi Mahamarg's 76 km stretch in Thane nears completion, set to open in August". The Indian Express. 28 May 2024.
  • ^ "'Mumbai-Nagpur highway set to become the fastest'". www.mid-day.com. 21 July 2021. Retrieved 6 August 2021.
  • ^ "40 pc work on Samruddhi Corridor completed, 623-km stretch to be operational by Dec 2021". The Indian Express. 29 July 2020. Retrieved 6 August 2021.
  • ^ "Mumbai: Samruddhi Mahamarg's Phase 1 inauguration to delay due to surge in COVID-19 cases; over 55% of project work attained". Free Press Journal. Retrieved 6 August 2021.
  • ^ "Samruddhi Mahamarg: Mumbai Nagpur Expressway Route Map, Progress and More - Infra Info Hub". 21 June 2024. Retrieved 21 June 2024.
  • ^ "Uddhav Thackeray to review Mumbai-Nagpur expressway work". The Hindustan Times. 5 December 2020.
  • ^ "Mumbai to Nagpur in 8 hours with super communication expressway on which fighter jets can land! 10 cool facts". The Financial Express. 15 January 2019. Retrieved 6 August 2021.
  • ^ Bhandari, Shashwat (30 June 2021). "Maharashtra's longest, widest road tunnel on Mumbai-Nagpur super expressway takes shape. Details". www.indiatvnews.com. Retrieved 6 August 2021.
  • ^ "710 किमी लांब, 6 पदरी रस्ता, 10 जिल्हे 392 गावातून जाणारा समृद्धी महामार्ग कसा आहे?". TV9 Marathi (in Marathi). 5 December 2020. Retrieved 6 August 2021.
  • ^ "Economics of Mumbai-Nagpur Expressway". 26 July 2017.
  • ^ "Samruddhi Expressway will turn runway in emergencies". 26 December 2019.
  • ^ Kulkarni, Dhaval (16 February 2017). "Maharashtra to begin work on first 'smart highway'". DNA India. Retrieved 30 July 2021.
  • ^ "Samruddhi Mahamarg to have over 11 lakh trees on both sides". www.thehitavada.com. Retrieved 6 August 2021.
  • ^ "Samruddhi Expressway will turn runway in emergencies". 26 November 2019.
  • ^ "Maharashtra Samruddhi Mahamarg: Things to know about India's 'fastest' highway". The Financial Express. 18 February 2021. Retrieved 2 August 2021.
  • ^ "Samruddhi Expressway will turn runway in emergencies". Free Press Journal. Retrieved 30 July 2021.
  • ^ "Mumbai to Nagpur in 8 hours with super communication expressway on which fighter jets can land! 10 cool facts". The Financial Express. 15 January 2019. Retrieved 6 August 2021.
  • ^ "Enhanced charging capacity on e-way, charging stations at 21 places on 701-km Mumbai-Nagpur Samruddhi Mahamarg". Lokmat English. 30 July 2021. Retrieved 2 August 2021.
  • ^ "Maharashtra Proposes To Spend Rs 9,453 Crore On EV Charging Centres". Moneycontrol. 8 March 2021. Retrieved 30 July 2021.
  • ^ "Mumbai to Nagpur in 8 hours with super communication expressway on which fighter jets can land! 10 cool facts". The Financial Express. 15 January 2019. Retrieved 6 August 2021.
  • ^ "Maharashtra Samruddhi Mahamarg: Things to know about India's 'fastest' highway". 18 February 2021.
  • ^ Kulkarni, Dhaval (16 February 2017). "Maharashtra to begin work on first 'smart highway'". DNA India. Retrieved 30 July 2021.
  • ^ Staff Reporter (8 October 2020). "Mumbai-Nagpur expressway will be ready by May 2022: MSRDC". The Hindu. ISSN 0971-751X. Retrieved 6 August 2021.
  • ^ "Fly ash utilisation in Samruddhi Mahamarg". www.firstconstructioncouncil.com. Retrieved 6 August 2021.
  • ^ "Mumbai to Nagpur in 8 hours with super communication expressway on which fighter jets can land! 10 cool facts". The Financial Express. 15 January 2019. Retrieved 6 August 2021.
  • ^ "Mumbai to Nagpur in 8 hours with super communication expressway on which fighter jets can land! 10 cool facts". 15 January 2019.
  • ^ "Maharashtra Samruddhi Mahamarg: Things To Know About India's 'fastest' highway - WorldNewsEra". 23 August 2020. Retrieved 6 August 2021.
  • ^ "Work on Nagpur–Mumbai Expressway begins in full swing". The Times of India. 22 January 2019.
  • ^ "Afcons asked to cough up Rs 238 crores fine for Murrum excavation". The Times of India. 29 December 2019.
  • ^ "PNC Infratech receives LoA for Nagpur–Mumbai Expressway project". Business Standard. 30 August 2018.
  • ^ "Reliance Infrastructure bags Rs 1,907 crores contract for Nagpur–Mumbai Expressway package-7". The Economic Times. 31 August 2018.
  • ^ "Montecarlo gets recovery notices for illegal mineral extraction". Outlook. 19 September 2020.
  • ^ "L&T wins Rs 2,095 crores orders for Nagpur–Mumbai Expressway". The Hindu. 4 September 2018.
  • ^ "Gayatri Projects receives Rs 1,312 crore road project in Maharashtra". The Economic Times. 3 October 2018.
  • ^ "Dilip Buildcon receives LoA for Nagpur–Mumbai Expressway project". Business Standard. 30 August 2018.
  • ^ "Maharashtra: Second wave of Covid-19 impacts construction of ambitious Samruddhi Mahamarg". The Times of India. 5 April 2021.
  • ^ "Townships, agri and industrial hubs planned along Mumbai-Nagpur e-way". 20 August 2020.
  • ^ "Mumbai-Nagpur expressway to become operational by May 2022". @businessline. 8 October 2020. Retrieved 6 August 2021.
  • ^ "These are the new 19 Townships of Maharashtra". Square Feat India. 11 October 2020. Retrieved 30 July 2021.
  • ^ "Nagpur-Mumbai Expressway: Maharashtra govt to offer cash, land to farmers". The Financial Express. 22 August 2016. Retrieved 30 July 2021.
  • ^ Jog, Sanjay (11 October 2016). "Mumbai-Nagpur super expressway: Villagers up in arms over land acquisition". Business Standard India. Retrieved 30 July 2021.
  • ^ Ravi, Reethu (27 June 2020). "Samruddhi Expressway To Get 10 Overpasses As Wildlife Mitigation Structures". thelogicalindian.com. Retrieved 6 August 2021.
  • ^ "National Wildlife Board issues final nod for Mumbai-Nagpur highway amid lockdown". Hindustan Times. 8 April 2020. Retrieved 30 July 2021.
  • ^ "Nagpur-Mumbai Expressway: A project designed with wildlife crossings". India Legal. 24 February 2021. Retrieved 30 July 2021.
  • ^ "'Fastest' land acquisition in Mumbai: How Nagpur-Mumbai expressway got farmers on its side". The Indian Express. 14 February 2021. Retrieved 30 July 2021.
  • ^ [ https://www.newindianexpress.com/states/telangana/2022/nov/29/nhai-to-build-mancherial-warangal-greenfield-highway-2523257.html NHAI to build Mancherial-Warangal greenfield highway], Indian Express, 29 nov 2022.
  • ^ Mega national highways projects: 22 expressways to be built in 5 years by 2024, 2020.
  • ^ Ghadyalpatil, Abhiram (14 July 2017). "Land acquisition for Mumbai-Nagpur expressway starts". Mint. Archived from the original on 13 July 2017. Retrieved 31 May 2018.
  • ^ "18 companies bid for Mumbai-Nagpur Expressway project". The Economic Times. 23 May 2018. Archived from the original on 31 May 2018. Retrieved 31 May 2018.
  • ^ "13 lowest bidders named for Samruddhi Mahamarg E-way". Free Press Journal.
  • ^ "Package 1". www.mahasamruddhimahamarg.com.
  • ^ Nair, Aishwarya (16 November 2018). "Samruddhi Mahamarg work to begin in December". The Asian Age.
  • ^ "Work on Nagpur-Mumbai expressway begins in full swing | Nagpur News - Times of India". The Times of India. 22 January 2019.
  • ^ "Mumbai News: समृद्धि महामार्ग 2022 से पहले तैयार हो जाएगा: शिंदे". Navbharat Times.
  • ^ "BJP's pet project, Mumbai-Nagpur expressway, likely to stay on track | Mumbai News - Times of India". The Times of India.
  • ^ "Land acquisition for Mumbai-Nagpur expressway still at 86% | Mumbai News - Times of India". The Times of India.
  • ^ "40% work on Samruddhi Corridor completed, 623 km stretch to be operational by December 2021". 29 July 2020.
  • ^ "Covid-19 Pushes Mumbai-Nagpur Highway Commissioning by 6 Months; No Cost Overruns". News18. 8 October 2020.
  • ^ "Mumbai–Nagpur Expressway to become operational by May 2022". Hindu Business Line. 8 October 2020.
  • ^ "कोरोना ने टाला समृद्धि महामार्ग का उद्‌घाटन, मई के बजाय अब सितंबर में शुरू हो सकता है पहला फेज". Navbharat Times. 4 May 2021.
  • ^ "Maharashtra's longest tunnel to be ready in a year, will cut Mumbai-Nagpur travel time by 1 hour". India Today. 10 July 2021.
  • ^ "Longest twin-tunnel on Mumbai-Nagpur expressway to be ready by Sep". The Hans India. 10 August 2021. Retrieved 19 September 2021.
  • ^ "In photos: Historic twin tunnels near Igatpuri on Mumbai-Nagpur expressway". The Times of India. 16 September 2021. Retrieved 19 September 2021.
  • ^ "Samruddhi Corridor: Nagpur-Shirdi stretch set for commissioning in May, says Maha minister". cnbctv18.com. 22 March 2022. Retrieved 27 March 2022.
  • ^ "Samruddhi Corridor: Nagpur-Shirdi stretch set for commissioning in May, says Maha minister". 20 April 2022.
  • ^ Tembhekar, Chittaranjan (22 April 2022). "First phase of Nagpur-Mumbai expressway to open on May 2". The Times of India. Retrieved 2 May 2022.
  • ^ "Wildlife overpass damaged, Mumbai-Nagpur expressway inauguration called off". The Indian Express. 26 April 2022. Retrieved 14 June 2022.
  • ^ "Much-Awaited Mumbai-Nagpur Expressway Opening Delayed Again". Mumbai Live. Retrieved 16 June 2022.
  • ^ "Mumbai-Nagpur expressway first part by August 15 | Mumbai News - Times of India". The Times of India. TNN. 18 July 2022. Retrieved 18 July 2022.
  • ^ Kukreja, Sahil (11 December 2022). "PM Modi inaugurates 'Samruddhi Mahamarg' Mumbai-Nagpur expressway: How it'll benefit car owners". The Times of India. Retrieved 11 December 2022.
  • ^ Phadke, Manasi (4 March 2023). "Shinde govt targets Dec 2023 finish for Nagpur-Mumbai Expressway, just ahead of state and LS polls". The Print. Retrieved 11 March 2023.
  • ^ Singh, Garima (26 May 2023). "Mumbai-Nagpur Expressway: CM Shinde, Dy CM Fadnavis Launch Phase-2 Of Samruddhi Mahamarg". Times Now News. Retrieved 26 May 2023.
  • ^ "17 Killed, 3 Injured In Crane Accident At Thane Expressway Site". NDTV.com. Retrieved 1 August 2023.
  • edit

    Retrieved from "https://en.wikipedia.org/w/index.php?title=Mumbai–Nagpur_Expressway&oldid=1232951403"
     



    Last edited on 6 July 2024, at 14:10  





    Languages

     



    ि
    Bahasa Indonesia

    Nederlands
    ி
     

    Wikipedia


    This page was last edited on 6 July 2024, at 14:10 (UTC).

    Content is available under CC BY-SA 4.0 unless otherwise noted.



    Privacy policy

    About Wikipedia

    Disclaimers

    Contact Wikipedia

    Code of Conduct

    Developers

    Statistics

    Cookie statement

    Terms of Use

    Desktop