Jump to content
 







Main menu
   


Navigation  



Main page
Contents
Current events
Random article
About Wikipedia
Contact us
Donate
 




Contribute  



Help
Learn to edit
Community portal
Recent changes
Upload file
 








Search  

































Create account

Log in
 









Create account
 Log in
 




Pages for logged out editors learn more  



Contributions
Talk
 



















Contents

   



(Top)
 


1 Incidence and impact of delays  





2 Analysis of delays  





3 Management solutions to delays  





4 See also  





5 References  





6 Further reading  





7 External links  














Construction delay







Add links
 









Article
Talk
 

















Read
Edit
View history
 








Tools
   


Actions  



Read
Edit
View history
 




General  



What links here
Related changes
Upload file
Special pages
Permanent link
Page information
Cite this page
Get shortened URL
Download QR code
Wikidata item
 




Print/export  



Download as PDF
Printable version
 
















Appearance
   

 






From Wikipedia, the free encyclopedia
 


Construction delays are situations where project events occur at a later time than expected due to causes related to the client, consultant, and contractor etc.[1] In residential and light construction, construction delays are often the result of miscommunication between contractors, subcontractors, and property owners. These types of misunderstandings and unrealistic expectations are usually avoided through the use of detailed critical path schedules, which specify the work, and timetable to be used, but most importantly, the logical sequence of events which must occur for a project to be completed.

Incidence and impact of delays[edit]

In more complex projects, problems will arise that are not foreseen in the original contract, and so other legal construction forms are subsequently used, such as change orders, lien waivers, and addenda. In construction projects, besides other projects where a schedule is being used to plan work, delays are likely to happen all the time. Delays in construction projects are frequently expensive, since there is usually a construction loan involved which charges interest, management staff dedicated to the project whose costs are time dependent, and ongoing inflation in wage and material prices.

Analysis of delays[edit]

What is being delayed determines if a project, or some other deadline such as a milestone, will be completed late. Before analyzing construction delays, a clear understanding of the general types is necessary. There are four basic ways to categorize delays:

Before determining the impact of a delay on the project, one must determine whether the delay is critical or non-critical. Additionally, all delays are either excusable or non-excusable. Both excusable and non-excusable delays can be defined as either concurrent or non-concurrent. Delays can be further broken down into compensable or non-compensable delays.

Management solutions to delays[edit]

Construction supply chain plays a major role in construction market competition. Construction supply chain management assists enterprises by helping to improve competitiveness, increase profits and have more control over the different factors and variables within the project.[citation needed] A. Cox and P. Ireland illustrated the myriad of construction supply chains which constitute the main flows within the construction supply chain.[2] In his research, Ghaith Al-Werikat analysed delays in relation to the myriad of construction supply chains. In particular, material flow,[citation needed] equipment flow,[citation needed] information flow,[citation needed] labour flow[citation needed] and client's information flow,[citation needed] offering a quantification of the impact of supply chain delays on construction projects performance. On the other hand, Economic historian Robert E. Wright argues that construction delays are caused by bid gaming, change order artistry, asymmetric information, and post contractual market power. Until those fundamental issues are confronted and resolved, many custom construction projects will continue to come in over budget, past due, or below contract specifications, he claims.[3]

See also[edit]

References[edit]

  1. ^ Sanni-Anibire, M. O., Mohamad Zin, R., & Olatunji, S. O. (2020). Causes of delay in the global construction industry: a meta analytical review. International Journal of Construction Management, 1-13.
  • ^ Cox, Andrew; Ireland, Paul (2002). "Managing construction supply chains: The common sense approach". Engineering Construction and Architectural Management. 9 (5–6): 409–418. doi:10.1046/j.1365-232X.2002.00273.x.
  • ^ Robert E. Wright, Fubarnomics: A Lighthearted, Serious Look at America's Economic Ills (Buffalo, N.Y.: Prometheus, 2010), 69-82.
  • Further reading[edit]

    External links[edit]


    Retrieved from "https://en.wikipedia.org/w/index.php?title=Construction_delay&oldid=1191886851"

    Category: 
    Building engineering
    Hidden categories: 
    Articles with short description
    Short description with empty Wikidata description
    All articles with unsourced statements
    Articles with unsourced statements from September 2020
    CS1 maint: multiple names: authors list
     



    This page was last edited on 26 December 2023, at 11:34 (UTC).

    Text is available under the Creative Commons Attribution-ShareAlike License 4.0; additional terms may apply. By using this site, you agree to the Terms of Use and Privacy Policy. Wikipedia® is a registered trademark of the Wikimedia Foundation, Inc., a non-profit organization.



    Privacy policy

    About Wikipedia

    Disclaimers

    Contact Wikipedia

    Code of Conduct

    Developers

    Statistics

    Cookie statement

    Mobile view



    Wikimedia Foundation
    Powered by MediaWiki