Jump to content
 







Main menu
   


Navigation  



Main page
Contents
Current events
Random article
About Wikipedia
Contact us
Donate
 




Contribute  



Help
Learn to edit
Community portal
Recent changes
Upload file
 








Search  

































Create account

Log in
 









Create account
 Log in
 




Pages for logged out editors learn more  



Contributions
Talk
 



















Contents

   



(Top)
 


1 Construction  





2 See also  





3 References  





4 External links  














Pajares Base Tunnel






Čeština
Deutsch
Español
Euskara
Français
Italiano
Magyar
Português
 

Edit links
 









Article
Talk
 

















Read
Edit
View history
 








Tools
   


Actions  



Read
Edit
View history
 




General  



What links here
Related changes
Upload file
Special pages
Permanent link
Page information
Cite this page
Get shortened URL
Download QR code
Wikidata item
 




Print/export  



Download as PDF
Printable version
 
















Appearance
   

 





Coordinates: 43°0110N 5°4631W / 43.01944°N 5.77528°W / 43.01944; -5.77528
 

From Wikipedia, the free encyclopedia
 


Works on portal

The Pajares Base Tunnel is a twin pair of railway tunnels beneath the Puerto de Pajares pass in the Cantabrian Mountains, Spain. The 24,667 m (80,928 ft) length tunnel form a key portion of the high-speed rail line between León and Gijón, and can be used by both high speed passenger trains as well as by slower freight trains.

Work commenced on the Pajares Base Tunnel following its authorisation in 2003. During the construction process, multiple setbacks were incurred on the part of the geological conditions present, particularly the copious ingress of water into the tunnels. Despite multiple years of remedial work and the deployment of unique engineering solutions, the infiltration issue has proved to be difficult to address, and questions have arisen as to if its electrification is even practical. As a result, the fitting-out of the tunnel has been delayed by several years. Early on, the through route was expected to be open in 2010. Finally, the tunnels were opened to passenger traffic the 30th November 2023.[1][2]

Construction[edit]

During the early decades of the 21st century, Spain allocated a large proportion of European Union-supplied infrastructure funding into the expansion of its AVE high speed rail network.[3] On 1 March 2002, it was announced that Gestor de Infraestructuras Ferroviarias (GIF) had awarded a €5·18m contract to Ineco and Geoconsult for the design of a new 50 km high speed railway between La Robla and Pola de Lena, forming a part of the main line between Madrid - Oviedo main line. The most prominent civil engineering work of this line is the twin-bore Pajares Base Tunnel, which necessitated a length of 24,667 m (80,928 ft) to traverse the Pajares pass of the Cantabrian Mountains.[4] It was reportedly regarded as being one of the largest and most challenging civil engineering projects anywhere in Europe at that time.[3] The tunnel would replace a relatively steep and winding conventional route through the mountains that had limited train speeds to a maximum speed of 70 kmph, while the new line was envisioned to facilitate speeds of up to 300 kmph.[5]

During 2003, the Public Works Ministry awarded a €1.8 billion contract for the Pajares Base Tunnel's construction to a consortium involving the majority of Spain’s major civil engineering firms, including FCC, Acciona, Dragados, Ferrovial, Sacyr, and Constructora Hispánica.[3] As originally planned, both bores of the Pajares Base Tunnel would have been furnished only with standard gauge high-speed rail; however, mid-way through construction, it was decided that a dual gauge arrangement would be installed instead, as it was thought that the presence of Iberian gauge would make the tunnel particularly useful to freight trains as well.[6] It had been anticipated that the completed tunnel would facilitate a journey time of 2 hours and 12 minutes between Madrid and Oviedo by 2010.[7]

Its execution began with five TBMs (four for the large tubes and the fifth for the gallery from Buiza) between July and September 2005 on the León slope and between April and July 2006 on the Asturian slope. The tunnel boring machines extracted 4.3 million m³ from the tunnels. The bulk of the excavation work for the Pajares Base Tunnel was performed by tunnel boring machines (TBMs).[7][8] The construction soon encountered substantial amounts of underground water, the presence of relatively porous karst in the vicinity of the bores had been previously identified by surveys undertaken in the 1980s; accordingly, vast quantities of water continuously infiltrated into the bores. It has been alleged by construction workers that management had prioritised maintaining a high rate of progress over properly sealing the tunnel against water infiltration.[3] Furthermore, the geological conditions surrounding the tunnel featured multiple areas of high compressive tectonic stress regimes, such as thrust faults, which necessitated greater levels of support to be installed in the tunnel than had been originally anticipated.[9][10] Despite this, the boring process was completed eight months ahead of schedule. On 11 July 2009, a ceremony was held to mark the completion of the tunnels.[3]

However, despite this milestone being attained, the fitting-out of the tunnel proceeded at a very slow rate due to the water infiltration issue; up to 2,200 liters of water was reportedly entering the tunnel every second, much of it via cracks in its concrete walls.[5] Conventional waterproofing measures, such as polymeric paste injection and polymeric membranes, proved insufficient, while additional excavation was prohibitively expensive due to the walls being largely complete already. Instead, engineers turned to unorthodox means of channeling the water by installing a first-of-its-kind composite lining.[5] After four years of work, the rate of water infiltration had been reduced by 40 percent.[7] By 2014, the difficulties of constructing the Pajares Base Tunnel had become thoroughly apparent.[3] Over the course of one decade, the initial plans of the tunnel were altered on 15 occasions. The costs of its construction has overrun substantially, rising to €3 billion against the originally budgeted price of €1.8 billion.[3]

During June 2020, it was announced that Administrador de Infraestructuras Ferroviarias (ADIF) had awarded a €53m contract to a consortium of Alstom, Indra and the San José Construction Group to supply tunnel safety and security systems for the 12 tunnels of the Pajares New Line project, including the Pajares Base Tunnel.[11] Despite plans for the tunnel to be electrified by 25 kV AC throughout its 24,667 m (80,928 ft) length, questions have been raised if electrification is feasible due to the high level of water infiltration present.[7]

See also[edit]

References[edit]

  1. ^ "Asturias goes through the time tunnel: great chronicle of the historic day in which the Variant saw the light". us.firenews.video. 30 November 2023. Retrieved 30 November 2023.
  • ^ "Spanish high-speed line under mountains opens after 20 years of construction". Trains. 2023-12-01. Retrieved 2023-12-03.
  • ^ a b c d e f g Mendez, Rafael (7 May 2014). "€1.2 billion over budget and still no opening date in sight". english.elpais.com.
  • ^ "Pajares base tunnel contract". railwaygazette.com. 1 March 2002.
  • ^ a b c Mason, Karen (7 January 2018). "Composites perform water rescue in high-speed rail tunnel". compositesworld.com.
  • ^ "Fomento prevé concluir las obras de la variante Pajares a finales de 2020". La Vanguardia (in Spanish). 15 June 2017. Retrieved 5 March 2020.
  • ^ a b c d Bent, Mike (Autumn 2014). "Pajares: A Wet, Warm Tunnel, and other White Elephants" (PDF). eurorail.org.uk.
  • ^ Pyeon, Jae-Ho (March 2016). "Trend Analysis of Long Tunnels Worldwide" (PDF). Mineta Transportation Institute.
  • ^ Hijazo, T. and Vallejo, L.I. (2012). "In-situ stress amplification due to geological factors in tunnels: The case of Pajares tunnels, Spain". Engineering Geology. s 137–138: 13–20. doi:10.1016/j.enggeo.2012.03.007.{{cite journal}}: CS1 maint: multiple names: authors list (link)
  • ^ Pablo Valenzuela, María José Domínguez-Cuesta, Mónica Meléndez-Asensio, Montserrat Jiménez-Sánchez, José Antonio Sáenz de Santa Marí (2015). "Active sinkholes: A geomorphological impact of the Pajares Tunnels (Cantabrian Range, NW Spain)". Engineering Geology. 196: 158–170. doi:10.1016/j.enggeo.2015.07.007. ISSN 0013-7952.{{cite journal}}: CS1 maint: multiple names: authors list (link)
  • ^ Cuenca, Oliver (20 July 2020). "Adif awards €53m systems contract for Pajares New Line project". railjournal.com.
  • External links[edit]

    43°01′10N 5°46′31W / 43.01944°N 5.77528°W / 43.01944; -5.77528


    Retrieved from "https://en.wikipedia.org/w/index.php?title=Pajares_Base_Tunnel&oldid=1210954269"

    Categories: 
    Railway tunnels in Spain
    Buildings and structures in Asturias
    Transport in Asturias
    Base tunnels
    Railway lines opened in 2023
    Tunnels completed in 2023
    Hidden categories: 
    CS1 Spanish-language sources (es)
    CS1 maint: multiple names: authors list
    CS1: long volume value
    Pages using gadget WikiMiniAtlas
    Articles with short description
    Short description is different from Wikidata
    Articles with Spanish-language sources (es)
    Coordinates on Wikidata
     



    This page was last edited on 29 February 2024, at 03:33 (UTC).

    Text is available under the Creative Commons Attribution-ShareAlike License 4.0; additional terms may apply. By using this site, you agree to the Terms of Use and Privacy Policy. Wikipedia® is a registered trademark of the Wikimedia Foundation, Inc., a non-profit organization.



    Privacy policy

    About Wikipedia

    Disclaimers

    Contact Wikipedia

    Code of Conduct

    Developers

    Statistics

    Cookie statement

    Mobile view



    Wikimedia Foundation
    Powered by MediaWiki