Jump to content
 







Main menu
   


Navigation  



Main page
Contents
Current events
Random article
About Wikipedia
Contact us
Donate
 




Contribute  



Help
Learn to edit
Community portal
Recent changes
Upload file
 








Search  

































Create account

Log in
 









Create account
 Log in
 




Pages for logged out editors learn more  



Contributions
Talk
 



















Contents

   



(Top)
 


1 Construction  





2 Services  





3 Fire  





4 References  














Victorian Big Battery






Français
 

Edit links
 









Article
Talk
 

















Read
Edit
View history
 








Tools
   


Actions  



Read
Edit
View history
 




General  



What links here
Related changes
Upload file
Special pages
Permanent link
Page information
Cite this page
Get shortened URL
Download QR code
Wikidata item
 




Print/export  



Download as PDF
Printable version
 
















Appearance
   

 





Coordinates: 38°02S 144°17E / 38.04°S 144.29°E / -38.04; 144.29
 

From Wikipedia, the free encyclopedia
 


Victorian Big Battery
Map
Country
  • Australia
Location
Coordinates38°02′S 144°17′E / 38.04°S 144.29°E / -38.04; 144.29
StatusOperational
Commission date
  • 8 December 2021
Owner(s)
Operator(s)
Power generation
Nameplate capacity
  • 300 MW
Storage capacity
  • 450 MW h
External links
Websitevictorianbigbattery.com.au

The Victorian Big Battery is a grid-connected battery electricity storage facility adjacent to the Moorabool Terminal Station (substation) near GeelonginVictoria, Australia. The battery provides 450 MWh of storage and can discharge at 300 MW. It surpasses the 250 MWh Gateway Energy StorageinCalifornia, United States.[1] As of December 2021, the project is the largest lithium-ion battery in the Southern Hemisphere.[2]

The Victorian Big Battery is owned and operated by French renewable energy producer Neoen. Funding of $160 million was provided by the Clean Energy Finance Corporation,[3][4] the Australian government's green bank.

Construction started at the beginning of 2021. It commenced operations on 8 December 2021.[5] It uses Tesla Megapack storage units, an electric accumulator designed specifically for large-scale projects.

The battery aims to prevent blackouts during periods of network instability by providing grid support services, capturing and storing excess energy from sources such as wind farms, and feeding it into the grid during peak periods or outages to support Victoria's electricity supply.[6] The battery will store enough energy to power more than half a million Victorian homes for an hour, or the homes of a population equivalent of Geelong (the city where it is situated) for two hours.

Construction

[edit]

Construction began in January 2021. The battery was scheduled to be commissioned in the Australian summer period 2021-2022 and has been in operation since December 8, 2021. For Neoen's battery, the EPC (Engineering, Procurement and Construction) contractor is Tesla, using UGL as the prime contractor. The connection assets are being provided by AusNet Services, with Downer as the prime contractor.

The storage unit uses 212 Tesla Megapacks, each with a capacity of 3 MWh. This will be the first time Megapacks have been used in a facility of this scale in Australia.

The battery is being built within AusNet's Moorabool Power Terminal in close proximity to the 500 KV high voltage line so that power can be sent quickly to where it is needed.

Construction of the battery was supported by a $160 million loan from the Clean Energy Finance Corporation, an agency owned by the Australian federal government.

Services

[edit]

Following a tender issued by the Victorian Government in 2020, Neoen was awarded a contract by the Australian Energy Market Operator to reserve approximately 80% of its capacity during the summer months to provide 250 MW of System Integrity Protection Scheme (SIPS) services. This will increase the transfer capacity on the Victorian/New South Wales interconnector during peak consumption periods and reduce the risk of unplanned power outages.

The remaining 50 MW of the battery can be commercially deployed in the market by the operator. Outside the summer period, the battery, with a total capacity of 300 MW, will be operated commercially.

With the services provided by the battery, average industrial electricity consumers could save as much as $280,000 per year on their bills. The Portland aluminium smelter could see its bills drop by as much as $1 million per year.[citation needed]

The battery is tested for grid inertia with 'grid forming' abilities.[7]

Fire

[edit]

During the initial testing of the energy storage system on 30 July 2021, a fire broke out in one of the Tesla Megapack modules and destroyed two battery units while the fire was left to burn itself out, as recommended. No injuries were reported. The battery pack had been placed into offline mode before the fire, and this had also isolated the monitoring and management systems. The site was disconnected from the grid, with no impact on the power supply. The system was isolated, and energisation testing was not permitted to resume until 29 September 2021. The cause of the fire was determined to have been a leak of cooling fluid that short-circuited cells to thermal runaway. Subsequent configuration changes mean that the monitoring remains active on offline battery packs.[8][9]

References

[edit]
  1. ^ "LS Power Energizes World's Biggest Battery, Just in Time for California's Heat Wave". www.greentechmedia.com. Retrieved 30 December 2021.
  • ^ "Neoen switches on Australia's biggest battery". yahoonews. Yahoo!. 8 December 2021. Retrieved 14 December 2021.
  • ^ Hartmann, Imogen. "$160 million for Victorian Big Battery – Energy Spurt". Retrieved 29 December 2021.
  • ^ Toscano, Nick (25 February 2021). "Federal green bank powers up Victoria's 'Big Battery' with $160m boost". Sydney Morning Herald. Retrieved 29 December 2021.
  • ^ "Neoen starts operating 300 MW Victorian Big Battery in Australia, one of the world's largest batteries" (PDF) (Press release). Neoen. 8 December 2021. Retrieved 13 December 2021.
  • ^ Rollason, Bridget (5 November 2020). "Victoria's new Tesla battery in Moorabool to drive down power prices, State Government says". ABC News. Australia. Retrieved 13 December 2021.
  • ^ Colthorpe, Andy (25 April 2023). "Grid inertia measurement trial at Australia's biggest battery storage project". Energy Storage News.
  • ^ Colthorpe, Andy (28 September 2021). "Tesla 450MWh Victorian Big Battery in Australia resumes testing after fire setback". Energy Storage News. Retrieved 13 December 2021.
  • ^ Colthorpe, Andy (11 May 2022). "Investigation confirms cause of fire at Tesla's Victorian Big Battery in Australia". Energy Storage News. Archived from the original on 11 May 2022.

  • Retrieved from "https://en.wikipedia.org/w/index.php?title=Victorian_Big_Battery&oldid=1225990633"

    Categories: 
    Energy storage projects
    Buildings and structures in Geelong
    Electric power infrastructure in Victoria (state)
    Energy infrastructure completed in 2021
    2021 establishments in Australia
    Hidden categories: 
    Pages using gadget WikiMiniAtlas
    Articles with short description
    Short description is different from Wikidata
    Use Australian English from December 2021
    All Wikipedia articles written in Australian English
    Use dmy dates from December 2021
    Infobox mapframe without OSM relation ID on Wikidata
    Coordinates on Wikidata
    All articles with unsourced statements
    Articles with unsourced statements from June 2022
    Pages using the Kartographer extension
     



    This page was last edited on 27 May 2024, at 23:23 (UTC).

    Text is available under the Creative Commons Attribution-ShareAlike License 4.0; additional terms may apply. By using this site, you agree to the Terms of Use and Privacy Policy. Wikipedia® is a registered trademark of the Wikimedia Foundation, Inc., a non-profit organization.



    Privacy policy

    About Wikipedia

    Disclaimers

    Contact Wikipedia

    Code of Conduct

    Developers

    Statistics

    Cookie statement

    Mobile view



    Wikimedia Foundation
    Powered by MediaWiki